一、工程概况 .................................................................................................................................................................... 3 二、编制依据 .................................................................................................................................................................... 4 三、N1线路用电计算 ...................................................................................................................................................... 4 1、施工机具 .................................................................................................................................................................. 4 2、供电系统设置 .......................................................................................................................................................... 5 3、 确定用电负荷: ..................................................................................................................................................... 5 4、1号干线线路上导线截面及分配箱、开关箱内电气设备选择: .......................................................................... 6 5、选择总箱的进线截面及进线开关: ...................................................................................................................... 10 6、临时供电施工图 .................................................................................................................................................... 10 四、N2线路用电计算 ..................................................................................................................................................... 12 1、施工机具 ................................................................................................................................................................ 12 2、供电系统设置 ........................................................................................................................................................ 13 3、确定用电负荷: ...................................................................................................................................................... 14 4、2号干线线路上导线截面及分配箱、开关箱内电气设备选择: ........................................................................ 18 5、选择总箱的进线截面及进线开关: ...................................................................................................................... 41 6、绘制临时供电施工图 ............................................................................................................................................ 42 五、N3线路用电计算 ..................................................................................................................................................... 54 1、施工机具 ................................................................................................................................................................ 54 2、供电系统设置 ........................................................................................................................................................ 55 3、确定用电负荷: ...................................................................................................................................................... 56 4、3号干线线路上导线截面及分配箱、开关箱内电气设备选择: ........................................................................ 59 5、选择总箱的进线截面及进线开关: ...................................................................................................................... 77 6、绘制临时供电施工图 ............................................................................................................................................ 78 六、施工临时用水计算书 .............................................................................................................................................. 88 1、工程用水量计算: .................................................................................................................................................. 88 2、机械用水量计算: .................................................................................................................................................. 89 3、工地生活用水量计算: .......................................................................................................................................... 90 4、生活区用水量计算: .............................................................................................................................................. 90 5、消防用水量计算: .................................................................................................................................................. 90 6、施工工地总用水量计算: ...................................................................................................................................... 90 7、供水管径计算: ...................................................................................................................................................... 90 七、安全用电技术措施 .................................................................................................................................................. 91 1、安全用电技术措施 ................................................................................................................................................ 91 2、安全用电组织措施 ................................................................................................................................................ 96 八、安全用电防火措施 ................................................................................................................................................ 101 1、施工现场发生火灾的主要原因 .......................................................................................................................... 101 2、预防电气火灾的措施 .......................................................................................................................................... 102 九、防雷装置设计 ........................................................................................................................................................ 103
1
施工临时用水用电施工方案
十、接地装置设计 ........................................................................................................................................................ 104 十一、附图 .................................................................................................................................................................... 105
2
施工临时用水用电施工方案
施工临时用水用电施工方案
一、工程概况
工程名称:国平·时代天街1#地块 工程地址:武隆县中堆坝
建设单位:重庆国平物业开发有限公司 设计单位: 重庆源道建筑规划设计有限公司 监理单位:重庆联盛建设项目管理有限公司 勘察单位:中国建筑西南地勘设计研究有限公司 施工单位: 重庆森佑建筑工程有限公司 质量监督单位:武隆县建设工程质量监督站 安全监督单位:武隆县建设工程安全监督站
承包方式:采用总承包管理责任制,由投标人对分包单位进行总体协调管理 施工承包范围:按施工承包合同范围 工期目标:520天日历工期 质量目标:一次验收合格
安全文明目标:创建重庆市安全文明工地 开工日期:以合同约定及开工报告为准 完工日期:以合同约定及开工报告为准 建设规模:总建筑面积84194.59m 2,其中住宅44691.46 m 2,车库18635.74 m 2,商业20641.36 m 2,配套用房226.03 m 2. 国平·时代天街1#地块 单体建筑特征表 栋使用层数 建筑面积户数建筑消防建筑基结构抗震工程号 功能 (m2 ) (户) 高度计算防火础类型 设防设计(m) 高度分类 形烈度 等级 (m) 式 1#住宅 25F/-1F 16595.95 159 79.8 79.9 一类桩剪力6° 一级 楼 高层基墙 2#住宅 25F/-1F 11681.06 92 79.8 79.9 建筑 础 楼 3#住宅 25F/-1F 16587.69 159 79.8 79.9 楼 1~商业 2F/-1F 11025.91 10.2 10.3 一类桩框架6° 二级 3#高层基结构 楼建筑础 裙的裙 房 房多 A#商业 4F/-2F 4671.31 18.6 18.7 层公共建三级 楼 B#商业 4F/-2F 4996.28 18.6 18.7 筑 楼 3
施工临时用水用电施工方案 地车库 下车库 小计 -2F 18545.31 车位数:499 I类桩坡道基式汽础 车库 84103.51 总户数:410 框架6° 结构 一级 二、编制依据
《低压配电设计规范》GB50054-2011中国建筑工业出版社
《建筑工程施工现场供电安全规范》GB50194-2014中国建筑工业出版社 《通用用电设备配电设计规范》GB50055-2011中国建筑工业出版社 《供配电系统设计规范》GB50052-2009中国建筑工业出版社 《施工现场临时用电安全技术规范》JGJ46-2005中国建筑工业出版社
《建筑施工安全检查标准》JGJ59-2011
《国平·时代天街1#地块总平面布置图》设计文件 建设方提供的水源及电源条件 施工用水、用电高峰期
三、N1线路用电计算
1、施工机具 序号 1 2 3 4 机具名称 钢筋调直机 钢筋切断机 钢筋弯曲机 白炽灯 型号 GT4/14 QJ40 GW40 安装功率(kW) 数量 4 7 3 0.1 1 2 2 20 合计功率(kW) 4 14 6 2 4
施工临时用水用电施工方案
2、供电系统设置
钢筋调直机开关箱 1号动力分箱 钢筋切断机开关箱 总配电箱 1号干线 钢筋弯曲机开关箱 1号照明分箱 白炽灯开关箱 3、 确定用电负荷: (1)、钢筋调直机
Kx=0.65,Cosφ=0.7,tgφ=1.02 Pjs=0.65×4=2.6kW
Qjs=Pjs×tgφ=2.6×1.02=2.65kvar (2)、钢筋切断机
Kx=0.65,Cosφ=0.7,tgφ=1.02 Pjs=0.65×14=9.1kW
Qjs=Pjs×tgφ=9.1×1.02=9.28kvar (3)、钢筋弯曲机
Kx=0.65,Cosφ=0.7,tgφ=1.02 Pjs=0.65×6=3.9kW
Qjs=Pjs×tgφ=3.9×1.02=3.98kvar (4)、白炽灯
Kx=1,Cosφ=1,tgφ=0 Pjs=1×2×1=2kW
Qjs=Pjs×tgφ=2×0=0kvar
(5)总的计算负荷计算,总箱同期系数取Kx=0.95 总的有功功率
Pjs=Kx×ΣPjs=0.95×(2.6+9.1+3.9+2)=16.72kW 总的无功功率
Qjs=Kx×ΣQjs=0.95×(2.65+9.28+3.98+0)=15.119kvar
5
钢筋调直机 钢筋切断机 钢筋弯曲机 白炽灯