小型构件预制场建设
方案
精品文档
目 录
1.编制依据及原则 ................................................................................................................................ 1 1.1编制依据 ....................................................................................................................................... 1 1.2编制原则 ....................................................................................................................................... 1 2.工程概况 ............................................................................................................................................ 1 3.预制场选址 ........................................................................................................................................ 1 4.施工进度安排 .................................................................................................................................... 2 5.小型构件预制场规划方案 .................................................................................................................. 2 5.1整体规划 ....................................................................................................................................... 2 5.2平面布置规划 ............................................................................................................................... 2 5.3施工用水方案 ............................................................................................................................... 3 5.4施工用电方案 ............................................................................................................................... 3 5.5养生措施 ....................................................................................................................................... 4 6施工方案 ............................................................................................................................................... 4 6.1测量放样 ....................................................................................................................................... 4 6.2场地处理 ....................................................................................................................................... 4 6.3临建材料堆放 ............................................................................................................................... 5 6.4防雨棚搭设 ................................................................................................................................... 5 6.5围墙 ............................................................................................................................................... 5 6.6排水设施 ....................................................................................................................................... 5 6.7场地硬化 ....................................................................................................................................... 5 7预制块施工 ........................................................................................................................................... 6 7.1预制块形状及尺寸 ....................................................................................................................... 6 7.2施工工艺流程 ............................................................................................................................... 7 7.3盖板预制 ..................................................................................................................................... 11 8安全保证措施 ..................................................................................................................................... 14 9质量保证措施 ..................................................................................................................................... 14 10环境保护措施及文明施工 ............................................................................................................... 15
收集于网络,如有侵权请联系管理员删除
精品文档
1.编制依据及原则
1.1编制依据
(1)《公路工程质量检验评定标准》JTGF80/1-2004; (2)《公路工程技术标准》 JTGB01-2003; (3)《工程测量规范》GB50026—2007; (4)《公路路基施工技术规范》JTGF10-2006;
(5)《公路土工合成材料应用技术规范》JTJ/T 019-98; (6)《公路工程施工安全技术规范》JTGF90-2015; (7)《公路建设项目环境影响评价规范》JTGB03-2006; (8)《公路排水设计规范》JTJ018-97。 1.2编制原则
按照“节约用地,安全施工,文明环保”的原则,确保工程实施过程中合理利用征地,各项施工工序安全顺利进行。
2.工程概况
本标段设计小型预制构件预制混凝土1.2万立方米,设置1个小型预制构件场,小型预制构件在小型预制构件场统一、集中预制,运输到现场进行安装。
3.预制场选址
将小型构件预制场布置在项目经理部,在场地西侧,统一规划,分区管理,距离拌和站较近,混凝土可通过传送带直接进入场地进行小型预制构件的施工。
混凝土拌和站、钢筋加工厂、预制梁场及小型构件预制场统一规划、集中管理,有利于项目整体管理,能够有效管控施工质量,安全及文明施工水平有效提升,此位置在钢筋加工厂后面有利于半
收集于网络,如有侵权请联系管理员删除
精品文档
成品和材料的运输。
4.施工进度安排
施工准备、小型构件预制场建设:2015年10月20日~2015年11月10日。
5.小型构件预制场规划方案
5.1整体规划
小型预制构件设生产区、养护区、成品区,并按照用途分区存放,场区内搭设防雨棚。 5.2平面布置规划
小型构件预制场长60m,宽33.5m,面积2010㎡,小型预制构件模板采用高强塑料模板,按照构件尺寸制作由专业厂家支座专用模具,预制盖板采用定型钢模进行预制施工。预制构件根据型号分区预制、分区养生及存放。预制构件安装一条生产线,流水化作业,生产线安设振动台。
收集于网络,如有侵权请联系管理员删除
精品文档
5.3施工用水方案
养生水主要和拌合站一起合用一个水井,地下埋设主水管先流到蓄水池,水循环利用,养生完再流进沉淀池,沉淀池三级沉淀以后再流进蓄水池。蓄水池砌37墙,结构尺寸5m×3m×1.5m,沉淀池砌24墙,结构尺寸4m×3m×1.5m,内外面用水泥砂浆抹面砼铺底。
5.4施工用电方案
施工用电以地方电为主,自发电为辅。结合地理位置、用电量及电源情况,小型构件预制场与拌合站共用630kVA变压器,并备用200kW的发电机1台。严格按照经总监办批复的《临时用电方案》进行施工。
小型构件预制场电缆采用架空式,根据不同区域的用电量大小,按三相五线制要求布置各种型号的配电柜。
收集于网络,如有侵权请联系管理员删除