郑州华电高科电力设备工程有限公司 江苏盐城射阳港电厂3#.4#机组
编制:
审核:
审批: 编制单位:山东军辉建设安装工程有限公司电除尘拆除
施工方案
2014年10月
目录
1. 2. 3. 4. 5. 6. 7. 8. 9.
工程概况··········································3 编制依据··········································3 作业前应具备的条件································3 主要施工机具····································· 4 组织机构及劳动力配置····························· 4 施工工期········································· 5 拆除的顺序及方法································· 5 安全措施········································· 6 危险点(源)····································· 10
10. 施工环境保护·································12 11. 施工进度计划·································12
一、工程概况
江苏盐城射阳港发电厂3#4#机组除尘器为电气除尘器,3#4#机组各对应一台除尘器,每台除尘器分为六个电场,大致设备有:除尘器支架、除尘器壳体、阴极板、阳极板、灰斗、冲灰器、阳极板振打器、阴极板振打器、检修电动葫芦、顶部布置有六台变压器及开关柜、系统管道及阀门、就地控制柜等,阴极板、阳极板悬挂在顶部支撑梁上。 拆除方式:变压器及开关柜、阴极阳极振打器电机、电动葫芦、手动及气动插板门、冲灰器、各种就地控制柜、测量元件为保护性拆除,除尘器支架、壳体、阴极板、阳极板、灰斗、进出口喇叭口、平台楼梯、除尘器范围内的各种管道为破坏性拆除。 二、编制依据
1、《建设工程安全生产管理条例》 2、《建筑施工高处作业安全技术规范》 3、《施工现场临时用电安全技术规范》 4、《电力建设安全健康与环境管理工作规定》 5、《火电施工质量检验及评定标准》(锅炉机组篇) 6、工程建设标准强制性条文(电力工程部分) (2006版) 7、射阳港发电厂下发的各种管理文件 三、作业前应具备的条件 1、电除尘拆除方案已批复。
2、电除尘拆除范围内的的各种水、汽、油系统与在用机组相隔断,并做好明显标记。
3、电除尘拆除范围内的电已永久性断掉。
4、电除尘拆除区域已围设完成,并挂有安全警示牌。 5、经过作业区域的在用管线已做可靠的保护措施。 6、使用的工器具已到位齐全并已检测合格。 7、设备、废料堆放周转性场地以划分。 8、安全通道已设立并挂有安全警示牌。 9、消防器材已布置到位。
10、应急预案已审批,应急物资已到位,应急组织机构已建立。 11、作业人员已到位,体检合格。
12、作业人员、管理人员已进行安全三级教育,考试已合格。 13、安全技术交底已进行,并实行全员签字。 14、特种作业人员资格审查已结束,并已合格通过。 15、起重机械已到位,并有有效的安全手续。 16、与电厂办理的各种手续已完成,并批准开工。 17、施工用电已布置完,符合安全使用要求。
四、主要施工机具 序 号 1 名 称 汽车吊 规格型号 50T以上 数 量 1台 备 注 经检验合格 2 汽车吊 20T 1台 经检验合格 3 平板车 1台 经检验合格 4 手拉葫芦 5T 8台 经检验合格 5 手拉葫芦 3T 10台 经检验合格 6 手拉葫芦 1T 10台 经检验合格 7 与手拉葫芦匹配的钢丝绳 若干 8 吊车用起重钢丝绳 若干 9 气割工具 6套 经检验合格 10 电焊机 2台 经检验合格 11 千斤顶 20T 2台 经检验合格 12 千斤顶 50T 2台 经检验合格 13 手提切割 5台 经检验合