恒大地产集团住宅室内装饰施工工艺和质量标准 - 图文

来源:用户分享 时间:2025/6/18 6:20:13 本文由loading 分享 下载这篇文档手机版
说明:文章内容仅供预览,部分内容可能不全,需要完整文档或者需要复制内容,请下载word后使用。下载word有问题请添加微信号:xxxxxxx或QQ:xxxxxx 处理(尽可能给您提供完整文档),感谢您的支持与谅解。

目录

第一章 住宅室内装修工序间歇及工艺间歇标准······························3 1.1墙面各工序间歇及工艺间歇要求标准··································· ········3 1.2地面各工序间歇及工艺间歇要求标准············································3 1.3木地板施工基层要求标准································································4 1.4细部处理各工艺间歇要求标准························································4 1.5其它装修施工要求············································································4 第二章 住宅室内装修工艺流程标准·····················································5 第三章 住宅室内装修施工工艺和质量标准····························· ···········6 3.1场地移交····························································································6 3.2弹线···································································································10 3.3电线穿管····················· ······································································14 3.4卧室地面找平···················································································15 3.5墙面砖铺装·······················································································17 3.6墙面石材铺装···················································································23 3.7天花吊顶、石膏线安装·····································································28 3.8入户门安装·······················································································31 3.9地面砖、石材铺贴·············································································34 3.10窗台石铺贴·····················································································40 3.11天花墙面扇灰、涂饰乳胶漆···························································42 3.12墙面造型制作、安装·······································································47 3.13橱柜、卫浴安装················································································51 3.14户内门安装······················································································57 3.15木地板安装······················································································63 3.16墙面玻璃镜面安装·········································································70

1

3.17墙面木饰面造型油漆·····································································70 3.18墙纸贴铺·························································································73 3.19阳台护栏安装·················································································77 3.20低窗护栏安装·················································································78 3.21墙面软包制作安装·········································································80 3.22灯具、插座开关面板安装·······························································82 3.23卫生洁具安装·················································································97 3.24卫浴五金安装···············································································104 3.25淋浴隔断安装···············································································105 3.26细部处理·······················································································106 3.27石材镜面处理···············································································114 3.28卫生清理·······················································································116

2

恒大地产集团

住宅室内装修施工工艺和质量标准(试行)

施工工序原则:先上后下、先湿后干、先内后外、先粗后细、先制作后安装。

第一章 住宅室内装修工序间歇及工艺间歇标准

1.1墙面各工序间歇及工艺间歇要求标准

≥28天 ≥28天 ≥15-20天 ≥7天 砌体 墙面抹灰 主体结构工艺要求 工艺要求 工艺要求 刮腻子涂料 \\ 墙纸 小高层 结构至8层,中高 层、高层结构施 工至12层时,砌体可开始施工。 1、 一次砌 筑高度不大于1.8米,间歇1天后再砌筑施工。 2、 顶砖(或 顶膨胀混凝土浇筑)施工,须砌体完成7天后进行。 1、 南方地区: 秋、冬季墙面含水率不大于12﹪,春、夏季墙面含水率不大于14﹪时可刮装饰腻子。 2、 北方地区: 统一控制墙面含水率不大于12﹪时即可刮装饰腻子。 1、 根据墙 面基层平整度,可进行2~3遍刮装饰腻子。 2、 每两遍 装饰腻子施工干燥间歇时间为不小于48小时。 1、 南方春、夏 季基层含水率不大于12﹪,北方地区及南方秋、冬季基层含水率均不大于8﹪。 2、 每两遍涂 料(墙纸基层底油)间歇时间为不小于48小时。

1.2地面各工序间歇及工艺间歇要求标准

1、卧室木地板、地毯等基层地面找平完成后,可上人作业间歇时

3

间为不小于48小时。

2、客厅、餐厅、厨房、卫生间、阳台、电梯前室、首层大堂等地面砖、石材铺贴完成后,可上人作业间歇时间为不小于48小时。

3、室内地面砖、石材及地面找平完成后,墙面1米线以下墙体刮装饰腻子需要间歇不小于15-20天,其要求含水率不大于14﹪。

1.3木地板施工基层要求标准

木地板地面基层含水率标准一览表

地区 南 季节 春、夏 秋、冬

1.4细部处理各工艺间歇要求标准

1、厨房、卫生间、阳台、电梯前室、首层大堂等墙面砖采用湿贴工艺,砖缝水泥清理所需间歇时间为3-6小时。

2、墙面、地面、台面等湿贴作业完成后,需钻孔、打眼等间歇时间不小于14天。

3、各交界面细部处理打胶后,与卫生清理间歇时间不小于24小时。 4、入户门门框安装后,门扇安装所需间歇时间不小于72小时;户内门门框安装后,门扇安装所需间歇时间不小于24小时。

1.5其它装修施工要求

1、小高层结构至8层,中高层、高层结构施工至12层,砌体开始施工时,装修施工单位定标、不少于2名装修管理人员到位。 3、外立面装饰完成10层,外脚手架拆除上面5层,且卫生清理

4

北 ≤8﹪ ≤8﹪ ≤12﹪ ≤8﹪

恒大地产集团住宅室内装饰施工工艺和质量标准 - 图文.doc 将本文的Word文档下载到电脑,方便复制、编辑、收藏和打印
本文链接:https://www.diyifanwen.net/c0nirj2bkk523x6i11fyp2nsft0iuth00r3s_1.html(转载请注明文章来源)
热门推荐
Copyright © 2012-2023 第一范文网 版权所有 免责声明 | 联系我们
声明 :本网站尊重并保护知识产权,根据《信息网络传播权保护条例》,如果我们转载的作品侵犯了您的权利,请在一个月内通知我们,我们会及时删除。
客服QQ:xxxxxx 邮箱:xxxxxx@qq.com
渝ICP备2023013149号
Top