XXXX五星级水疗度假酒店
XXXX五星级水疗度假酒店项目
防雷接地专项施工方案
编制人: 审核人: 审批人:
XXXX集团XXXX有限公司 XXXX五星级水疗度假酒店项目部
2016年12月
第1页 共19页
XXXX五星级水疗度假酒店
目录
第一章 工程概况 ································································································· 3 第一节 基本概况 ······························································································ 3 第二节 防雷接地概况 ························································································ 3 第二章 编制依据 ································································································· 3 第三章 施工准备 ································································································· 4 第一节 技术准备 ······························································································ 4 第二节 材料准备 ······························································································ 4 第三节 工器具 ································································································· 4 第四章 施工工艺 ································································································· 5 第一节 屋面防雷施工工艺 ·················································································· 5 1、避雷针施工要点 ························································································································ 5 2、避雷针安装示意图 ···················································································································· 5 第二节 引下线施工工艺 ····················································································· 7 1、引线线施工要点 ························································································································ 7 2、引下线连接示意图 ···················································································································· 7 第三节 等电位连接施工工艺················································································ 9 1、总等电位连接示意图 ················································································································ 9 2、卫生间等电位连接 ·················································································································· 10 3、泳池等电位连接 ······················································································································ 11 第四节 基础接地施工工艺 ················································································· 12 1、基础接地施工要点 ·················································································································· 12 2、基础接地示意图 ······················································································································ 12 第五章 质量保证措施 ·························································································· 14 第一节 质量标准 ····························································································· 14 第二节 应注意的质量问题 ················································································· 14 第三节 质量记录 ····························································································· 15 第六章 安全保证措施 ·························································································· 16 第七章 现场文明体系及施工措施 ··········································································· 17 第一节 绿色施工环境管理方针、目标及工程环境管理体系 ········································ 17 第二节 文明施工 ····························································································· 17 第三节 施工现场垃圾清除安排············································································ 18 第四节 环境保护 ····························································································· 18
第2页 共19页
XXXX五星级水疗度假酒店
第一章 工程概况
第一节 基本概况
本工程建筑包括总服务区一个,建筑面积3150m2;海滩烧烤活动区一处,房屋面积136 m2;水疗中心一处,房屋面积720 m2;海滩别墅33座,房屋面积2084 m2;环礁湖群柱架空式套房47座,房屋面积2746 m2;花园群柱架控式套房15套,房屋面积836 m2;帝王别墅一座,房屋面积1012m2;皇家别墅2座,房屋面积1060 m2。
强电专业:高压配电系统,变配电系统,UPS系统,照明系统,动力系统,防雷接地系统。
弱电专业:火灾报警系统,有线电视系统,电话网络系统,监控系统,房间背景音乐,客房服务,舞台影院系统等。
给排水专业:给水系统,污废水系统,灌溉系统,海水淡化,游泳池水处理,消防系统,雨水系统。
暖通专业:分体空调和空气冷凝机系统,防排烟系统。
第二节 防雷接地概况
工程避雷采用避雷针形式,沙滩别墅不设置避雷针,帝王别墅,皇家别墅,总服务区设置避雷针。本工程配电系统接地型式为TN-S,在每户配电箱进线引入处,PE线做重复接地,并做等点位连接。
第二章 编制依据
1、工程文件:《开工令》、《总承包工程承诺书》、《投标技术文件》 ; 2、施工图纸:《建筑设计方案》;
3、公司有关质量管理、安全管理、现场文明施工管理和各种工序工法的标准程序文件;
4、现场条件及周边场地情况。 5、图集及相关规范
第3页 共19页
XXXX五星级水疗度假酒店
第三章 施工准备
第一节 技术准备
1、施工前,专业工长必须认真研读设计图纸,编制《防雷接地施工方案》,并按要求向监理单位报审;
2、防雷接地工程施工前,专业工长必须对施工班组进行全面细致的技术交底。
第二节 材料准备
防雷与接地工程使用的主要材料为圆钢、镀锌扁钢、电线等,使用材料必须符合设计规定,产品应有材质检验证明及产品出厂合格证。
第三节 工器具
1、项目根据具体的施工工艺要求准备施工所需的机械,专业工长、安全员负责检查,检查合格方能进场使用。
2、施工主要机械及器具为: 序号 1 2 3
第4页 共19页
设备名称 型号规格 数量 额定功率(KW) 生产能力 切割机 Y100L-2 3 2 4 2.2KW 1.5 KW 完好 完好 角向磨光机 BS-100 交流电焊机 ZX1-315 11KW,220V 完好