l29, the company responsible for a variety of procedures for reimbursement document, invoice review, approval of work; 30, regularly convened general meeting of shareholders, preparation work for the meeting; 31, the company responsible for payroll management jobs, including around salary survey, employee salary, salary accounting methods developed, payroll accounting, payment of wages, bonuses; 32, the company responsible for delivery of financial procedures; 33, according to the company's strategic development plan, the preparation and management of funds to meet day-to-day operating funding requirements to ensure the company's safety, liquidity and profitability of the funds; 34, responsible for the environmental protection building materials Corporation issued by the Corporation Annual, monthly economic indicators in the assessment of the economic responsibility system of proposed amendments; 35, the company responsible for all types of contracts and tracking, implementation, implementation of the agreement, abnormality was detected in time to take appropriate measures and feedback to the leadership; 36, regular inspection, analysis, budget implementation of the business and financial performance, and to propose measures to increase revenue and reduce expenditure; 37, responsible for organizing the company's contracting business tenders; 38, responsible for preparing the annual budget and final accounts, distribution of profits, loss compensation plan; 39, responsible for the violations of financial discipline, or damage the company's interests (corruption and bribery) review of the Act; 40, 移动通信基站铁塔基础监理计划及细则
监理计划
1、接到业主的开工通知及清单后及时与各县公司建维管理人员联系,确认具体的开工站点。
2、接到施工单位的复线申请后,山区在8小时内,其余地区在5小时内到达现场进行复核。
3、及时掌握已开工站点的施工进度,对于验收地槽提前2天通知市公司建维部管理员。
4、对混凝土浇筑、机房内土方回填实行旁站。
5、经常性的对已施工的站点进行巡视,发现问题及时解决。对于发现的可能影响到工程安全性和可能引起造价增加的问题,及时向业主汇报。
6、随时与设计和地质勘探方保持联系。
监理细则 一、 监理依据
1、工程建设监理合同
2、施工招投标文件及工程施工合同 3、设计文件及图纸
4、建筑法、建设工程质量管理条例、工程建设监理规程以及有关工程建设和建设监理的法律、法规、政策、规定。 5、国家现行建设工程的施工及验收规范。
l29, the company responsible for a variety of procedures for reimbursement document, invoice review, approval of work; 30, regularly convened general meeting of shareholders, preparation work for the meeting; 31, the company responsible for payroll management jobs, including around salary survey, employee salary, salary accounting methods developed, payroll accounting, payment of wages, bonuses; 32, the company responsible for delivery of financial procedures; 33, according to the company's strategic development plan, the preparation and management of funds to meet day-to-day operating funding requirements to ensure the company's safety, liquidity and profitability of the funds; 34, responsible for the environmental protection building materials Corporation issued by the Corporation Annual, monthly economic indicators in the assessment of the economic responsibility system of proposed amendments; 35, the company responsible for all types of contracts and tracking, implementation, implementation of the agreement, abnormality was detected in time to take appropriate measures and feedback to the leadership; 36, regular inspection, analysis, budget implementation of the business and financial performance, and to propose measures to increase revenue and reduce expenditure; 37, responsible for organizing the company's contracting business tenders; 38, responsible for preparing the annual budget and final accounts, distribution of profits, loss compensation plan; 39, responsible for the violations of financial discipline, or damage the company's interests (corruption and bribery) review of the Act; 40, 二、 通则
1、原材料质量管理:所有进场的使用于工程上的材料均在监理的
参与下共同取样并共同送检测机构检验。对于检测机构检验不合格的材料立即清退出施工现场。
2、混凝土试件的取样、制作在监理方的见证下进行。 3、检查其他材料的质量是否符合规范规定的质量要求。 4、安全管理措施
(1)用电安全:电线、电缆一律架空,不随地乱放;用电器具一律“一机一闸一漏电保护”,整个配电系统采用三级漏电保护;挖孔施工时的井内照明采用36V电压。
(2)防护安全:整个施工区域全封闭并设置安全警示标志;桩孔在不施工时一律加盖盖板并有专人看护。
(3)桩孔内通风:桩孔深度超过6米时采用人工强制通风。
三、 质量控制要点
1、人工挖孔桩
(1)定位检查
在全部桩位定位放线完毕后进行复核并检查放线误差,各个桩位要准确,桩与桩之间的误差控制在3MM之内,两条对角线之间的差控制在5MM之内。
(2)桩孔检查
①土质:会同设计、地质勘探方共同验槽,必须符合设计要求,如实际土质不符合设计要求,则要求设计、地质勘探方提出处理方案并
l29, the company responsible for a variety of procedures for reimbursement document, invoice review, approval of work; 30, regularly convened general meeting of shareholders, preparation work for the meeting; 31, the company responsible for payroll mnagement jobs, including around salary survey, employee salary, salary accounting methods developed, payroll accounting, paymnt of wages, bonuses; 32, the company responsible for delivery of financial procedures; 33, according to the company's strategic development plan, the preparation and management of funds to meet day-to-day operating funding requirements to ensure the company's safety, liquidity and profitability of the funds; 34, responsible for the environmental protection building materials Corporation issued by the Corporation Annual, monthly economic indicators in the assessment of the economic responsibility system of proposed amendments; 35, the company responsible for all types of contracts and tracking, implementation, implementation of the agreement, abnormality was detected in time to take appropriate measures and feedback to the leadership; 36, regular inspection, analysis, budget implementation of the business and financial performance, and to propose measures to increase revenue and reduce expenditure; 37, responsible for organizing the company's contracting business tenders; 38, responsible for preparing the annual budget and final accounts, distribution of profits, loss compensation plan; 39, responsible for the violations of financial discipline, or damage the company's interests (corruption and bribery) review of the Act; 40,督促实施。
②深度:必须符合设计要求。
③直径:与设计数值的误差必须不大于20㎜(包括扩大头)。 ④桩孔垂直度检查:吊线垂检查桩孔的垂直度,偏差控制不超过25㎜。
(3)钢筋笼的检查:检查是否根据设计图进行钢筋笼的制作。检查螺旋箍与纵向钢筋的各个交点与纵向钢筋焊接是否牢固(焊点处不得有纵向钢筋受伤情况),全部焊渣是否已清除干净,加强箍的位置是否准确,钢筋保护层是否已按规定尺寸垫好。
(4)塔脚螺栓的预埋:检查四个预埋螺栓的顶部是否在一个水平面上,每个螺栓之间的误差不大于3MM,两条对角线之间的差值不大于5MM。
(5)混凝土施工
①混凝土施工前检查孔内是否有积水,如有积水督促施工方及时清除,混凝土浇灌前孔内的积水和沉渣厚度不得大于50MM。
②混凝土浇灌:进行前检查混凝土的配合比是否正确;计量器具及机具是否已经准备就绪;混凝土的坍落度控制在7CM左右。
2、独立柱及片筏基础 (1)定位检查
在全部柱位定位放线完毕后进行复核并检查放线误差,各个柱位要准确,柱与柱之间的误差控制在3MM之内,两条对角线之间的差控制在5MM之内(片筏基础检查外部尺寸是否正确)。
l29, the company responsible for a variety of procedures for reimbursement document, invoice review, approval of work; 30, regularly convened general meeting of shareholders, preparation work for the meeting; 31, the company responsible for payroll management jobs, including around salary survey, employee salary, salary accounting methods developed, payroll accounting, payment of wages, bonuses; 32, the company responsible for delivery of financial procedures; 33, according to the company's strategic development plan, the preparation and management of funds to meet day-to-day operating funding requirements to ensure the company's safety, liquidity and profitability of the funds; 34, responsible for the environmental protection building materials Corporation issued by the Corporation Annual, monthly economic indicators in the assessment of the economic responsibility system of proposed amendments; 35, the company responsible for all types of contracts and tracking, implementation, implementation of the agreement, abnormality was detected in time to take appropriate measures and feedback to the leadership; 36, regular inspection, analysis, budget implementation of the business and financial performance, and to propose measures to increase revenue and reduce expenditure; 37, responsible for organizing the company's contracting business tenders; 38, responsible for preparing the annual budget and final accounts, distribution of profits, loss compensation plan; 39, responsible for the violations of financial discipline, or damage the company's interests (corruption and bribery) review of the Act; 40, (2)基坑检查:
①土质:会同设计、地质勘探方共同验槽,必须符合设计要求,如实际土质不符合设计要求,则要求设计、地质勘探方提出处理方案并督促实施。
②基坑尺寸:深度必须符合设计要求;底部尺寸不小于设计值。 (3)钢筋检查:检查是否根据设计图进行钢筋的制作及安装;检查钢筋的接头位置是否正确;检查安装好的钢筋骨架是否洁净,钢筋保护层是否已按规定尺寸垫好。
(4)塔脚螺栓的预埋:检查四个预埋螺栓的顶部是否在一个水平面上,每个螺栓之间的误差不大于3MM,两条对角线之间的差值不大于5MM。
(5)混凝土施工
①混凝土施工前检查基坑内是否有积水及其他杂物,如有督促施工方及时清出,混凝土浇灌前基坑内不得有积水和其他杂物。
②混凝土浇灌:进行前检查混凝土的配合比是否正确;计量器具及机具是否已经准备就绪;混凝土的坍落度控制在5-7CM。
3、机房及围墙 (1)保证项目
① 屋面不得有渗漏。检查方法:观察、中间检查。 ② 室内外回填土必须密实。检查方法:旁站、中间检查。 ③ 电气器具必须符合设计规定。检查方法:中间检查。 (2)基本项目
l29, the company responsible for a variety of procedures for reimbursement document, invoice review, approval of work; 30, regularly convened general meeting of shareholders, preparation work for the meeting; 31, the company responsible for payroll mnagement jobs, including around salary survey, employee salary, salary accounting methods developed, payroll accounting, paymnt of wages, bonuses; 32, the company responsible for delivery of financial procedures; 33, according to the company's strategic development plan, the preparation and management of funds to meet day-to-day operating funding requirements to ensure the company's safety, liquidity and profitability of the funds; 34, responsible for the environmental protection building materials Corporation issued by the Corporation Annual, monthly economic indicators in the assessment of the economic responsibility system of proposed amendments; 35, the company responsible for all types of contracts and tracking, implementation, implementation of the agreement, abnormality was detected in time to take appropriate measures and feedback to the leadership; 36, regular inspection, analysis, budget implementation of the business and financial performance, and to propose measures to increase revenue and reduce expenditure; 37, responsible for organizing the company's contracting business tenders; 38, responsible for preparing the annual budget and final accounts, distribution of profits, loss compensation plan; 39, responsible for the violations of financial discipline, or damage the company's interests (corruption and bribery) review of the Act; 40,①混凝土抗压强度:不低于设计值;试块检测报告 ②轴线允许误差:+10MM,-5MM;用尺量 ③门扇开闭灵活:现场开闭门扇。 ④外墙面基本平整:检查方法:观察。
⑤内墙面基本平整、色泽基本一致:检查方法:观察。 ⑥预留洞口符合设计要求:检查方法:观察。
安徽省建设监理有限公司 安庆移动通信基站工程监理部
二00四年八月二日