目 录Content
一、编制依据Basis of edit 1
二、筒体结构滑模施工技术方案cylinder slip forming construction technical plan
1
三、生料库滑模施工RAW MILL SILO SLIP FORMING CONSTRUCTION ........... 2
(一) 滑模工艺设计design of slip forming technics ................................................ 2 (二) 外筒滑模平台设计design of out cylinder slip forming platform ................... 3 (三) 内筒滑模平台设计design of inner cylinder slip forming platform ................ 6 (四) 油路布置disposal of oil route .......................................................................... 9 四、库壁结构滑升施工工艺SILO WALL STRUCTURE ELEVATING
CONSTRUCTION TECHNICAL ................................................................................... 10
(一) 滑升区段的划分elevation section division ................................................... 10 (二) 滑模平台组装slip forming platform installation .......................................... 10 (三) 组装顺序installation sequence ......................................... 错误!未定义书签。 (四) 组装注意重点installation attention point...................................................... 11 (五) 一个浇灌层滑模施工工艺流程one pouring layer's slip forming construction
technical flow .................................................................................................. 13 (六) 始滑first slip .................................................................................................. 14 (七) 钢筋和钢绞线绑扎reinforcing steel bars and bars tendon colligation ......... 14 (八) 预留洞reserved holes..................................................................................... 16 (九) 混凝土振捣concrete vibration....................................................................... 16 (十) 滑升sliding up ................................................................................................ 17 (十一) 平台的偏移及扭转的测量与控制flat form excursion & deviation measure and control ............................................................................................................. 18 (十二) 操作平台的拆除和改装flat form back out and refit ................................ 20 五、滑模模板shuttering
............................................................................................................................................. 20 六、垂直运输VERTICAL TRANSPORTATION ......................................................... 20 七、应急措施及注意事项EMERGENCY METHOD AND NOTICED PROCEEDING ............................................................................................................................................. 21
(一) 应急措施emergency method ......................................................................... 21 (二) 施工注意事项construction attention items ................................................... 21 八、安全技术措施SAFETY REGULATION ON SITE ............................................... 22
一、编制依据Basis of edit
1)工程施工图;Project construction drawings 2)工程招标文件;Project public bidding document
3)工程相关的施工规范、规程及相关的质量评定标准;Project related construction
criterion, regulation and related quality assess standard
4)液压滑动模板施工技术规范(GBJ113-87);Hydraulic slip shuttering construction
technology regulation
5)液压滑动模板施工安全技术规程(JGJ65-89);Hydraulic slip shuttering construction
technology and safety regulation
6)建筑机械使用安全技术规程(JGJ33-2001)。Safety and technology regulation of
using construction machines
二、筒体结构滑模施工技术方案
Cylinder slip forming construction technical plan
筒仓结构系按滑升模板工艺设计,滑升模板工艺系一次组装模板,连续浇灌成形,确保高质量地完成本工程的筒仓施工,做到内外壁圆滑无模板接痕,外壁做到清水滑模效果。
Cylinder silo structure is designed according to sliding up shuttering technology. Sliding up shuttering technology is that once install the shuttering and continue pouring to form to insure the accomplishment of high quality cylinder silo construction. It can make the inner and outer wall smooth without any shuttering connection mark and make the outer wall get the effect of rinsing slip forming.
1) 全部用GYD-60大吨位千斤顶、Φ48×2.75钢管作滑模支承杆。
All slip forming support poles will use large tonnage jack and Φ48×2.75steel tube. 2) 简化滑模平台,实际只设人行通道,即减轻平台荷载又方便施工。
It should simplified slip forming platform. Actually just set up a walking passage, which will reduce platform load as well as keep facility of construction
3) 柔性模板接缝之间夹一条海棉条,可以有效地防止板缝漏浆,同时使板缝拼接平
整、圆滑,提高筒仓结构滑模的外观质量
There is one piece sponge in the joint of flexible shuttering, which can effectively prevent leakage from the joint and at same time keep the joint flat, smooth to improve the appearance of the cylinder silo structure slip forming
4) 滑模工程外观不好的另一主要原因是水泥浆沿筒壁流淌,为防止操作平台上水泥
的流淌,在模板下口和模板间用Ф6夹海绵条吸附水泥浆,操作人员在每层及时清理海绵内的水泥浆。
Another reason for slip forming appearance drawback is that grout flow along cylinder wall. In order to stop the grout from control platform, use Ф6 sponge between shuttering below gob and shuttering to absorb grout. Controllers should clear up the group from sponge in each layer in time
5) 出模混凝土的处理措施:对出模混凝土及时进行原浆压光和对流淌水泥浆进行铲
除,在吊架上环绕筒壁设一圈Ф20铸铁管,在管上靠筒壁一侧均匀钻孔,用管道泵将水压入铸铁管,随滑模施工对筒壁混凝土进行喷淋。并派专人用清水均匀涂刷筒壁,最终达到表面圆滑、光洁、色泽基本一致的效果,同时在内外筒壁刷混凝土养护液养生。
Disposal measure of out shuttering concrete: press the out shuttering concrete to smooth in time and remove the flowing grout. On the scaffolding set a Ф20 cast iron tube around cylinder wall, drill equal holes on the tube next to cylinder wall, use tube pump compress water into cast iron tube, and then water can be sprayed to the concrete on cylinder wall during slip forming construction. Also special man should be arranged to brush the cylinder wall smoothly with clean water. Finally consistent effect of surface smooth, color and lustre will achieve. At the same time brush concrete maintenance liquid on inside and outside cylinder wall to maintain 三、生料库滑模施工Raw meal silo slip forming construction 1.滑模工艺设计Design of slip forming technics
根据图纸设计,生料库为预应力钢筋砼结构,外筒高 m,内径为 m,壁厚 m以下为 mm,以上为 mm,内筒高 m,内径为 m,壁厚为 mm,外筒每米砼量约为 m3,内筒每米砼量约为 m3,为保证砼的输送,在库外设一台塔吊和两台布料车进行施工。
According to drawing design, raw mill silo is pre-stress bar concrete structure. Out cylinder is m high, inner diameter is m, wall is m thick, above is mm and below is mm, inner cylinder is m high, inner diameter is m, wall is mm thick. Concrete quantity per meter of out cylinder is m3, Concrete quantity per meter of inner cylinder is m3 In order to keep concrete transport, 1 tower crane and 2 material trucks prepared out of the silo for construction.
外筒筒壁从基础顶标高开始采用滑模施工,滑至标高10.8m处,空滑至13.6m标高,施工内筒及减压锥底板。待减压锥底板施工完毕后改装滑模平台滑至77.2m。 Out cylinder wall begins slip forming construction from foundation top elevation. After slide to 10.8m elevation, slide with empty concrete to 13.6m elevation where reach the construction inner cylinder and decompress cone bottom board. After decompress cone bottom board construction finish, refit the slip forming platform and slide to 77.2m 2.外筒滑模平台设计
design of out cylinder slip forming platform
1)筒壁布置提升架和千斤顶,平台构件布置见平面布置图。
Set hoist frame and jack beside cylinder wall. Platform components disposal see plane disposal drawing
2)筒体平台荷载计算:Cylinder platform load calculation
根据设计滑模装置的荷载参考值,模板、围圈及提升架等自重、摩阻力按模板面积计算,操作平台及吊架自重、施工荷载按平台面积计算。
According to designed reference number of slip forming equipment load, deadweight, rub resistance of shuttering, pen and hoist frame, etc are calculated on shuttering acreage, while control platform, tower crane deadweight and construction load is calculated on platform acreage.
S模板shuttering=214.78㎡,S平台platform=420.60㎡ 序号No. 荷载名称load name 内外平台及吊架自重inside and outside platform and 1 tower crane deadweight 1.0×420.6=420.6 荷载值(KN)load number 模板、围圈及提升架自重shuttering, pen and hoist 2 3 4 5 3)千斤顶需用量计算Calculation of needed jack
千斤顶最少需用量计算calculation of jacks minimum number needed:n=N/P=1399.628/30=47台
综合考虑抗风要求和构造、稳定性等因素实际布置千斤顶76台,提升架76榀,千斤顶和提升架的布置详见滑模平面结构布置图。
Well think of the factors about anti-wind requirement and structure, stability, etc 76 jacks and 76 hoist frames are actually disposed. Detailed disposal of Jack and hoist frame see slip forming plane disposal drawing
千斤顶实际承载能力计算:The actual load capacity calculation: P=N/n=1399.628/76=18.5KN<30KN 故安全。So it is safe 4)支承杆计算supporting pole calculation
千斤顶爬升用支承杆采用Ф48×3.5脚手架钢管,每根支承杆的实际承受荷载18.5KN。 jack rising supporting pole will useФ48×3.5 scaffolding steel tube. And each n supporting pole’s actual load is 18.5KN 支承杆容许荷载计算
supporting pole admitting load calculation :P0=a×f×φ×An 式中formula:
P0--------支承杆允许承载力(KN);Supporting pole admitting load weight
f----------支承杆钢材强度设计值,取20KN/cm2;Supporting pole steel intensity designing figure
An-------支承杆截面积为4.89 cm2;Supporting pole section area is 4.89 cm2 a------工作条件系数,取0.7;Working condition modulus
φ-----轴心受压杆件的稳定系数,计算出杆的长细比λ值,查现行《钢结构设计规范》得
frame deadweight 摩阻力rub resistance 施工荷载construction load 总荷载total load 0.8×214.78=171.824 1.8×214.78=386.604 1.0×420.6=420.6 1399.628 φ值。λ=(0.75L1)/1.58
Stability modulus of pressed poles in axes. Calculate the length and thinness ratio λ
checked attachment from present “steel structure design regulation” will get φ
L1-----支承杆计算长度。按提空时最不利的状态计算,模板下口至千斤顶下卡头距离
195cm。Supporting pole length calculation. Suppose the worst condition calculation during empty rise, the distance between shuttering bottom hole and jack bottom clip head is 195cm
以上数据代入上式得:put above data into the formula make: λ=(0.75×195)/1.58=93 查表取值check from table φ=0.6 P0=0.7×20×0.6×4.89 =41.084KN>18.5KN;
即按照整个滑模平台托空时的最不利状态计算,支承杆的承载能力大于实际负荷,故十分安全。
That is when calculate on the basis of the worst condition during the whole slip forming platform empty load, supporting pole’ s load capacity is larger than actual load. So it is very safe.
5)液压系统设计hydraulic pressure system design a、液压系统计算hydraulic pressure system calculation 序号No 参数名称reference name 滑模装置总荷载slip 1 forming total load 2 千斤顶油缸容积jack V=0.261×n=0.261×76=19.84L oil tank capacity 千斤顶活塞总面积jack piston total area 千斤顶弹簧总压力4 jack spring total Pt=0.3n=0.3×76=22.8KN A=7457×n=7457×76=566732mm2 equipment N=1399.628KN 参 数 值reference number 3 pressure 5 所需工作压力required P=[ (N+Pt)/A+ΔP]/η=[(1399.628+22.8)×working pressure 1000/566732+0.1]/0.6=4.19MPa 6
齿轮泵流量gear pump Q=V·K/t=19.84×1.2/1=23.81L/min flux b、液压系统选型hydraulic pressure system types selection
选用HY-56型液压控制台,其技术参数如下:selecting HY-56 hydraulic pressure control platform, technology reference will be as follow:
HY-56型液压控制台HY-56 hydraulic pressure control platform
参数名称reference 参数名称reference 参 数 值reference 参 数 值reference number name name number 工作压力working pressure 最高压力the highest pressure 流量flux 8MPa 油箱容积oil tank capacity 电机功率electrical engine power 56L 10MPa 56L/min 10KW 3. 内筒滑模平台设计Design of inner cylinder slip forming platform 1)筒壁布置提升架和千斤顶,平台构件布置见平面布置图。
Set hoist frame and jack beside cylinder wall. Platform components disposal see plane disposal drawing
2)筒体平台荷载计算:Cylinder platform load calculation
根据设计滑模装置的荷载参考值,模板、围圈及提升架等自重、摩阻力按模板面积计算,操作平台及吊架自重、施工荷载按平台面积计算。
According to designed reference number of slip forming equipment load, deadweight, rub resistance of shuttering, pen and hoist frame, etc are calculated on shuttering acreage, while control platform, tower crane deadweight and construction load is calculated on platform acreage.
S模板=149.22㎡,S平台=298.43㎡
序号No. 荷载名称load name 内外平台及吊架自重inside and outside platform and tower 荷载值(KN)load number 1 crane deadweight 模板、围圈及提升架自重shuttering, pen and hoist frame 1.0×298.43=298.43 2 3 4 5 deadweight 摩阻力rub resistance 施工荷载construction load 总荷载total load 0.8×149.22=119.376 1.8×149.22=268.596 1.0×298.43=298.43 984.832 3)千斤顶需用量计算Calculation of needed jacks 千斤顶最少需用量计算calculation of jacks minimum number needed:n=N/P=984.832/30=33台
综合考虑抗风要求和构造、稳定性等因素实际布置千斤顶40台,提升架40榀,千斤顶和提升架的布置详见滑模平面结构布置图。
Well think of the factors about anti-wind requirement and structure, stability, etc 40 jacks and 40 hoist frames are actually disposed. Detailed disposal of Jack and hoist frame see slip forming plane disposal drawing
千斤顶实际承载能力计算:The actual load capacity calculation of the jack: P=N/n=984.832/40=24.62KN<30KN 故安全。So it is safe 4)支承杆计算supporting pole calculation
千斤顶爬升用支承杆采用Ф48×3.5脚手架钢管,每根支承杆的实际承受荷载24.62KN。Jack rising supporting pole will useФ48×3.5 scaffolding steel tube. And each supporting pole’s actual load is 24.62KN
支承杆容许荷载计算supporting pole admitting load calculation:P0=a×f×φ×An 式中:formula
P0--------支承杆允许承载力(KN);Supporting pole admitting load weight
f----------支承杆钢材强度设计值,取20KN/cm2;Supporting pole steel intensity designing figure adopt 20KN/cm2
An-------支承杆截面积为4.89 cm2;Supporting pole section area is 4.89 cm2 a------工作条件系数,取0.7;Working condition modulus adopt 0.7
φ-----轴心受压杆件的稳定系数,计算出杆的长细比λ值,查现行《钢结构设计规范》附
表得φ值。λ=(0.75L1)/1.58
Stability modulus of pressed poles in axes. Calculate the length and thinness ratio
λ check attachment from present “steel structure design regulation” will get φ
L1-----支承杆计算长度。按提空时最不利的状态计算,模板下口至千斤顶下卡头距离
195cm。Supporting pole length calculation. Suppose the worst condition calculation during empty rise, the distance between shuttering bottom hole and jack bottom clip head is 195cm
以上数据代入上式得:Put above data into the formula make: λ=(0.75×195)/1.58=93 查表取值check from tableφ=0.6 P0=0.7×20×0.6×4.89 =41.084KN>24.62KN;
即按照整个滑模平台托空时的最不利状态计算,支承杆的承载能力大于实际负荷,故安全。
That is when calculate on the basis of the worst condition during the whole slip forming platform empty load, supporting pole’ s load capacity is larger than actual load. So it is safe.
5)液压系统设计 Hydraulic pressure system design a、液压系统计算 Hydraulic pressure system calculation
序号参数名称reference No. name 滑模装置总荷载1 slip forming N=984.832KN equipment total load 2 千斤顶油缸容积jack oil V=0.261×n=0.261×40=10.44L tank 参 数 值reference number capacity 千斤顶活塞总面积3 jack piston total A=7457×n=7457×40=298280mm2 area 千斤顶弹簧总压力4 jack spring total Pt=0.3n=0.3×40=12KN pressure 所需工作压力5 required pressure 6 b、液压系统选型 hydraulic pressure system types selection
选用HY-56型液压控制台,其技术参数如下:selecting HY-56 hydraulic pressure control platform, technology reference will be as follow:
HY-56型液压控制台HY-56 hydraulic pressure control platform
参数名称reference name 工作压力working pressure 最高压力the highest pressure 流量flux 参 数 值reference number 参数名称reference name 油箱容积oil tank capacity 电机功率10MPa electrical engine power 56L/min 10KW 参 数 值reference number 56L P=[ (N+Pt)/A+ΔP]/η=[(984.832+12)× working 1000/298280+0.1]/0.6=5.74MPa 齿轮泵流量gear Q=V·K/t=10.44×1.2/1=12.53L/min pump flux 8MPa 4. 油路布置disposal of oil route
千斤顶的油路布置原则,应使千斤顶尽可能地同步工作,达到压力传递均匀,方便控制和纠偏的目的。不同结构类别的滑模工程,其油路布置是不一样的。而千斤顶位置随
着提升架的布置而确定。
Principle of jack oil route disposal is that taking every means to make jacks work synchronize, so that pressure can be delivered equally and reach the aim of convenient to control and rectify. Different type structure of slip forming project, its oil route disposal is different. While the location of the jack is fixed with the disposal of hoist frame 本工程拟采用三级分组并联油路布置,一级主油管选用19mm高压耐油橡胶管,二级分油管选用13mm高压耐油橡胶软管,支油管选用10mm高压软管伸向各千斤顶;分油器采用无缝钢管制作。一级分油器,一进六出(根据建筑平面每一方各一条分油路);二级分油器一进三出,各主油管长度和直径均取其相等,并作环形布置有利于均衡滑升;三级分油器一进六出通向各千斤顶,每级、每组均设有截流阀加以控制,千斤顶单独设针形阀,这样方便纠编和抽拔支承杆。
This project is planning to adopt 3 class groups and parallel connection of oil disposal. The first class main oil pipe will choose 19mm high pressure and oil endurance rubber pipe. The second class separate oil pipe will choose 13mm high pressure and oil endurance rubber pipe. Branch oil pipe will choose 10mm high pressure tube to run out to each jacks. Oil separator will adopt seamless steel pipe for manufacture. The first class oil separator will come out 6 parts after 1 enter (according to construction plane, each side should have one oil route). The second oil separator will come out 3 parts after 1 enter. Length and diameter of each main pipe are all selected the same. And rounding disposal will be used in favor of equilibrium sliding up. The third oil separator will come out 6 parts after 1enter to each jack. Every class and every group will dispose a shutting valve to control. Jacks will separately use needle valve, which be convenient to rectify and pull out the supporting pole.
四、库壁结构滑升施工工艺Silo wall structure elevating construction technical 1. 滑升区段的划分Elevation section division
根据经济和可行的原则考虑,从基础顶标高开始的竖向结构采用滑模工艺施工。 Think of the economic and feasible principle, from the foundation top the vertical structure adopt slip forming technology to construct
2. 滑模平台组装Slip forming platform installation 滑模平台结构详见《滑模平台布置图》。
Slip forming platform structure see “slip forming platform disposal drawing”
首先按滑模平台结构设计要求将结构加工完后,对各部件单元进行试组装,然后运至
现场,在基础顶标高处进行组装,严格控制组装时的测平和轴线的准确位置和垂直度。组装前应先绑扎1200㎜高的钢筋,以上的钢筋和钢绞线为边滑边绑扎。
First finish the structure manufacture according to slip forming platform structure design requirement. And try installing each unit parts. Then transport to site, and install them on the foundation top elevation part. When installing, strictly control the level testing and axes line’s exact position and vertical degree. Before installation 1200mm height reinforcing steel bar should be tied. The above reinforcing steel bar and bar tendon are sliding as well as tying.
3. 组装顺序Installation sequence
准确弹出各轴线和边框线以及筒壁的内外边线→按布置图准确定出各支承杆和千斤顶的位置→按准确位置布置提升架→安装围檩桁架→千斤顶定位→插支承杆→安模板→铺平台板→油路系统→电气系统→安全设施→拆除安装脚手架→滑至2m以后,安装吊脚手架。、
Exactly make out each axes line and frame line and inside and outside cylinder wall line→Exactly fix the location of each supporting pole and jack according to disposal drawing→set up hoist frame according to exact location→set up purlin joist supportor→fix the location of jacks→build in the supporting shaft→put shuttering→put platform board→oil route system→electrical system→safety establishment→back out the setting scaffolding→after slide to 2m, set suspending scaffolding
4.组装注意重点Installation attention point
滑模装置组装的允许偏差allowed deviation of slip forming equipment installation
允许偏差项 目 内 容subject content allowed deviation(mm) 模板结构轴线与相应结构轴线位置location of shuttering structure axes line and related structure axes line 3 水平方向horizontal 围檩位置偏差deviation of purlin location direction 3 垂直方向vertical direction 3 平面内in the plane 3 提升架垂直偏差vertical deviation of hoist frame 平面外out of plane 2 安放千斤顶的提升架横梁相对标高compared elevation of hoist frame beam for setting jacks 考虑倾斜度后模板宽度的偏差(倾斜度0.2-0.5%,以模板1/2高处为结构截面尺寸)(本工程上口-3㎜,下口+3㎜)shuttering width deviation after think of 5 上口upper gap -1 gradient(gradient0.2-0.5%, 1/2 height part of the shuttering 下口bottom gap +2 is the structure section dimension) ( this project upper gap-3mm, bottom gap+3mm) 提升架平面内in 千斤顶安装位置的偏差deviation of jacks location setting hoist frame plane 5 提升架平面外 out of hoist frame plane5 模板边长的偏差deviation of shuttering border length 相邻两块模板平面平整度偏差plane deviation of the near two shuttering 安装好后的模板应上口小下口大,单面倾斜宜为模板高度的0.2~0.5%,以模板高1/2处的净间距为结构截面标准尺寸。本工程定为模板上口-3㎜,模板下口+3㎜。作为模板组装标准。
After shuttering installation, the upper gap should be small, while bottom gap should be big. Single flat incline should be 0.2~0.5% of shuttering height and treat 1/2 shuttering height part distance as structure section standard dimension. This project makes that shuttering upper gap is -3mm and shuttering bottom gap is +3mm, which will be the standard of shuttering installation.
反复核对各轴线位置及壁厚是否与设计图纸相符。
Well check the location of each axes line and also check that if the wall thickness is in accordance with the drawing
5 2 对照施工图及支承杆布置图,将支承杆调整至准确位置。
Compare with the construction drawing and supporting pole disposal drawing, adjust the supporting pole to the exact location
对各支承杆作出测平标志,标定各即位卡,作好即滑准备。Make flat testing sign for each supporting pole, well mark each location wedge, and prepare for sliding. 5.一个浇灌层滑模施工工艺流程
One pouring layer's slip forming construction technical flow
筒壁竖筋绑扎时,相邻钢筋接头应设计图纸及规范错开,且同一水平截面接头数不超过竖筋总数的25%。水平环筋和钢绞线随滑升速度分层绑扎,必须严格按设计要求进行焊接,每相邻接头至少相隔3层环筋。内外层钢筋有“∽”形拉结筋定位,按设计要求梅花形布置。混凝土分层浇灌,每层高度20--30cm,筒体预埋件、预留孔随滑升速度与绑扎钢筋同时进行埋设和预留。滑模千斤顶支承杆接头采用双绑条单面焊。出模砼内外筒壁采用原桨压光,外壁要求达到清水模板效果,终凝后浇水养护。 When tying reinforcing steel bar to cylinder wall, near by steel bars’ connection part should be deviate from designed drawing and regulation. And the number of connection part on the same horizontal section is not over 25% of the total steel bars’ number. Horizontal rounding reinforcing steel bar and bar tendon will tie layer by layer according to sliding up speed. It must be strictly follow the design requirement to weld, and every near by connection part should be apart at least 3 layer rounding reinforcing steel bar. Inside and outside layer the reinforcing steel bar have “∽” type pulling reinforcing steel bar to fix the location. And make a cinquefoil disposal according to design requirement. Concrete should be poured layer by layer. And each layer is 20-30cm high. Embedded cylinder body and retained holes will be embedded and retained as sliding up speed and reinforcing steel bar tying
一个浇灌层滑模施工工艺流程图:
One pouring layer’s slip forming construction technical flow drawing
绑扎钢筋和钢绞线,焊接支承杆→浇砼20--30cm→滑升→垂直观测纠偏纠扭→铁件预埋、孔洞预留→找平、移限位卡→出模混凝土加原浆压光,在达到一定强度后用清水涂刷。Tying reinforcing steel bar and bar tendon, weld supporting pole→pouring concrete20—30cm→sliding up→vertical observation for rectifying deviation and wrest→embedding iron piece, retaining holes→checking for flat, moving limit wedge→adding original slurry to press and polish after concrete out of shuttering, and use
clean water to brush when it is reaching a certain intensity. 6.始滑first slip
内外模组装好,经反复核查无误后,清除模板内杂物即可扎始滑段的水平筋和固定埋件,对施工缝进行处理,油路、电气、砼输送系统均正常运转达后,方可浇灌砼。始滑第一层砼浇筑厚度30cm,滑升两个行程(5cm);再浇30cm,再滑升5cm,再浇30cm,即完成始滑过程而转入正常滑升。
After inside and outside shuttering installation finish and well check to find no mistake, clear up the rubbish inside the shuttering and then horizontal reinforcing steel bar can be tied on slip commencement section and embedded piece can be fix, and construction seam can be disposed. After Oil rount, electric and concrete transport system are all well working, then concrete pouring can be started. During first slip, concrete pouring thickness of first layer is 30cm, and after sliding up 2 times (5cm), pouring another 30cm, and then sliding up another 5cm, after pouring 30cm once more, and then first slip finish and change to usuall sliding up.
7.钢筋和钢绞线绑扎Reinforcing steel bars and bars tendon colligation
钢筋在地面制作好后,分批由塔吊运至滑模平台上,为配合滑模快速施工的需要,竖向钢筋采用绑扎搭接接头;均匀、排列有次,检测允许偏差必须达优良标准。竖筋按6m(1/2成品钢筋长度)分段,环筋12m(成品钢筋长度)分段,竖筋、环筋接头错开率均为1/4。
After reinforcing steel bars are finished manufacture on the ground, they will be partly taken to slip forming platform by tower crane. In order to cooperate slip forming fast construction, vertical reinforcing steel bar will adopt tying joint connection part. Equilibriums, arranged in order and check that allowed deviation must achieve good standard. Vertical reinforcing steel bar divided in every 6m (it is 1/2 length of finished reinforcing steel bar). Rounding reinforcing steel bar divided in every 12m (the length of finished reinforcing steel bar). All deviation rate of vertical and rounding reinforcing steel bar are 1/4
钢绞线在地面制作好后,分批由塔吊运至滑模平台上,先确定钢绞线的位置,焊接钢绞线托架,穿钢绞线并安装埋设预应力锚板。
After bar tendon are finished on the ground, they will be partly taken to slip forming platform by tower crane. First fix the location of bar tendon, weld bar tendon supporter, and then go through bar tendon and set up embedded pre-stress anchor board.
支承杆一律采用为Ф48×3.5钢管,全部采用焊接,支承杆的接头,在同一截面内按25%均匀布置,支承杆的标准长度定为6m,在开始时初始长度分别为1.5m、3m、4.5m、6m,各占1/4,依次排列,以后均按标准长度接长,接头接好后用砂轮打磨光滑,待千斤顶过后加焊钢筋帮条。第一段支承杆插入千斤顶后,不要落在混凝土面上,预留50cm,待试滑时,再插到位。
Supporting poles will be all usingФ48×3.5 type steel tube and all welding. Connecting part of supporting poles will be 25% equally dispose on the same section. Standard length of supporting pole is 6m. at the beginning, each preliminary length are separately 1.5m, 3m, 4.5m, 6m, while each one takes 1/4. they will be arranged one by one, and after that standard length will be used. After connecting parts are well connected, they will be polished by grinding. And after jack, weld supporting reinforcing steel bar. After first part supporting pole insert the jack, it should not be dropped on the concrete. Retain 50cm and insert it to the right location when trying slipping.
施工时应注意把筒壁的双排主筋和钢绞线绑扎好,并把处于其中立筋扶正。为了做好这一工作可采用钢筋导板或钢筋梳子定位。钢筋导板的做法是用50×100mm的方木沿筒壁宽度两侧布置,固定的提升架上,方木上钉有短板,短板上钻有按主筋间距布置的圆孔,主筋通过圆孔插放。这样即保证了细长主筋的稳定,也保证了钢筋的准确位置,同时洞口也可通过木枋进行固定。
When construction attention should be take on the two line main reinforcing steel bar and bar tendon tying. And make the vertical reinforcing steel bar straight among them. In order to well finish this job, reinforcing steel bar plank and comb can be used to fix the location. Method of making reinforcing steel bar plank is to dispose 50×100mm wood pieces along cylinder wall two width side. On fixed hoist frame and wood pieces, there will be some short board. And round holes are arranged on short board according to main reinforcing steel bar distance. Main reinforcing steel bar will insert the round holes. In this way, slim main reinforcing steel bar can be stable, and ensure the fixed location of reinforcing steel bar, and also wood pieces can be used to fix on the holes.
8.预留洞 Reserved Holes
筒壁的滑模施工是比较快的,因此,筒壁中的预留洞留设应事先做好准备工作,以便及时、准确无误地配合滑模施工进行留设。
Silo wall slip forming work is fast, so it should prepare reserved holes on silo wall to coordinate with slip forming team in time and acoup sur.
本工程应专门绘制预留洞,预埋件图,指派专人负责实施留设,以免遗漏。 This project should be protract reserved hole, embed part drawing and arrange In-charge person who is responsible for work to avoid missing.
事先按筒壁厚度设计制作做好洞口的留设钢模架衬模;通用部分可重复使用,应进行专门设计,做成工具式的,要求既要装拆灵活,又不易变形,确保洞口的形状、位置正确。预留洞衬模应比模板上口尺寸小5~10㎜,以便从滑模上口插入,同时又不会被滑模夹紧而上提发生位移。待滑升至设计标高时,将衬模从滑模上方插入安放于设计位置,并在顶部加水平钢筋压牢固定,外侧用短筋焊于墙筋或支承杆上予以固定。衬模与滑模接触点采用嵌海绵条的方法防止漏浆。
According to cylinder wall thickness design, make the reserved steel forming mold of the hole mouth in advance. Current part can be repeat used. It should de special designed and makes it to instrument style. Make it easy to install and remove, while difficult to change the form, so that the shape of the hole mouth and location is sure to be right. Reserved holes’ liner mold is 5~10mm less than the dimension of shuttering upper mouth, so that it can insert from the upper mouth of slip forming, and at the same time it will not be moved up because it is clamped by slip forming. When it is reach the designed elevation, put the liner mold into the designed location from slip forming up side, and fix it by pressing horizontal reinforcing steel bar on the top and the side part will be fixed by welding short reinforcing steel bar to wall reinforcing or supporting poles. Liner mold and slip forming connecting point will use sponge wedge to avoid leakage.
边长、直径小于1m的孔洞,支承杆穿过时一般不用加固;支承杆穿过尺寸大于1m的孔洞时,以洞边为支撑点,用钢管、扣件对支承杆进行硬性加固。
Those holes that length and diameter is less than 1m are generally no need to reinforce when supporting poles go through. When supporting poles go through those holes that
dimension is larger than 1m, then make the hole border a supporting point, and use steel 9.混凝土振捣 Concrete Vibration
用插入振捣器均匀捣实,每次浇注高度严格控制在20--30cm,每层浇捣的间隔时间不超过2小时,振捣器插入深度以不超过下层砼顶面5cm为限,不碰钢筋和模板,浇灌和振捣的顺序采用顺时针、逆时针交叉进行,浇上层砼时,下层砼必须处于塑性状态,即下层砼不超过初凝时间。控制出模强度在0.2~0.4Mpa之内。
Concrete should be vibrating in well proportioned. Every pouring height must controlled in 20cm-30cm, vibrator do not embed more than 5cm from surface of under layer and do not touch steel bar and shuttering. Pouring and vibrating adopted will desil and anticlockwise. When pouring superstratum concrete, the under layer concrete should be in plastic condition (under layer concrete do not over preliminary setting time). Concrete hardness should be 0.2Mpa -0.4 Mpa. 10.滑升 Sliding Up
初滑阶段,必须对滑模装置和砼凝结状态进行检查。
Preliminary sliding up should inspect slip forming equipment and concreting.
滑升过程中,两次滑升的时间间隔不超过1.5h,在气温较高时,应增加1~2次中间提升,中间提升高度为1~2个行程。
During sliding up, interval time do not more than 1.5 hours. When temperature is high, should increase 1 or 2 time lifting, center lifting height is 1-2 courses.
提升时,应使所有千斤顶充分进油、排油;提升过程中,如出现油压增至正常滑升油压的1.2倍,尚不能使全部液压千斤顶顶时,应停止提升操作,立即检查原因及时处理。
When sliding up, all jacks in and out oil should be well. During the sliding up, if find out even oil pressure increase to normal oil pressure 1.2 times, slip forming jack can not lifting, should be stop operation and make inspection immediately.
在滑升过程中,操作平台应保持水平,千斤顶的相对标高差不得大于40㎜,相邻两个提升架上千斤顶升差不得大于20㎜。
During the sliding up, flat form should keep balance, jack‘s relative elevation difference should not more than 40mm, border upon hoist frame jack’s lifting difference should not more than 20mm.
在滑升过程中,应检查和记录结构的垂直度,扭转及结构截面尺寸等偏差数值。 During sliding up, should check and record structure vertical degree, excursion and cross section deviation equivalence and so on.
在滑升过程中,应随时检查操作平台,支承杆的工作状态及砼凝结状态,如发现异常,应即时分析原因并采取有效的处理措施。
During sliding up, should inspect flat form, backstop work condition, concreting at any time, if find something wrong, should analyze reason and find solution for it immediately. 应即时清理粘结在模板上的砼浆和转角模板及活动模板之间的夹灰,对被油污染的钢筋和砼应及时处理干净。
Should clean concrete slurry, corner shuttering, dust between movable shuttering, oil polluted steel bar and concrete in time. 因故不能滑升时,应采取停滑措施。
It should adopted stop sliding up method if there is something wrong. 砼出模强度宜控制在0.2~0.4Mpa,或贯入阻力值为0.3~1.05KN/cm。
Concrete out shuttering stiffness should control under 0.2-0.4Mpa or adding resistance 0.3-1.05KN/cm.
11.平台的偏移及扭转的测量与控制 Flat form Excursion & Deviation Measure and Control
1)在方便观测的平台架一角,设置观测标志,用钢管分别从两方挑出,并在钢管上用醒目的油漆绘上经纬仪观测零点及左右10cm的刻度线,以便随时观测平台的偏移和扭转情况,至少每滑0.3m测量一次,并作好记录,即时采取措施进行纠正;在滑升过程中可采取倾斜平台法,徐缓纠偏;当滑空后可用机械外力作一次纠偏,使模板回复正确位置。
Set up observation indicator beside of flat form angle, use two steel pipe as indicator and paint theodolite observation zero point, about 10cm graduated scale to observe flat form excursion and deviation, at least sliding up 0.3M, it should observe one time and make a record for correction; Deviation of the platform shall be corrected by inclining in slow speed. When empty slip happens, use the out mechanical force to rectify it and make shuttering return to the right location.
2)在操作平台上,每滑升50~60cm作一次水平测量并将水平标高用红油漆标于各
支承杆上,调整各千斤顶和限位卡,以控制平台均衡提升,纠正倾斜或扭转,或用水箱胶管对每个千斤顶的水平进行检查,即时调整其升差。
On flat form, sliding up 50-60cm, make a horizontal measure and paint red marks on supporting shaft as horizontal level, adjust jack and limit switch to control balance of flat from, correct excursion and deviation or use water tank hose make inspection for every jack to adjust lifting tolerance.
3)平台纠扭:平台扭转采用牵拉法,沿周边均布8个点用手拉葫芦与扭转方向反向牵拉,平台提升时达到反向纠扭。
Correct deviation of Flat form adopted pulling method. Set 8 equal points around the edge and use hand hoist to pull reverse the running direction to realize the reverse twist. 4)垂直偏差的测量同时用重球法进行,在筒壁底部适当位置作十字观测标志,用20kg重Ф3㎜钢绳挂于平台架上,用卷筒控制,随滑升调整高度,以便随时观测。 Measurement of vertical difference adopted heavy ball method. Make a “+” sign observation mark at the bottom of silo, use 20kg , 3mm steel rod hung from flat form , use rolling cylinder to control, follow sliding up adjust height in order to take easy observation.
5)在纠正结构垂直偏差时,应徐缓进行,避免出现硬弯。
Correct structure vertical difference should be slow speed to avoid inflection.
6)滑模施工工程结构的允许偏差如下表 Slip Forming Construction Structure Allowed Tolerance as Follow:
项 目 内 容 Content 允许偏差 Allowed Tolerance(mm) Cross section of Silo Wall 库壁直径Silo Wall Diameter 0.1% , Not more than ±25 标高 Level 垂直度Vertical 全高 High ±30 High 0.1% not more than±50 Degree 每 7.5 米高仓身 7.5M high Storehouse ±25 柱、梁、壁、截面尺寸 Pole, girder, wall cross section dimension 门窗洞口及预留洞口的位置偏差 Position Difference of door, window and obligate wall hole 预埋件位置偏差 Embed Position Difference 12.操作平台的拆除和改装 Flat form Back out and Refit
+10 -5 15 20 1)生料库外筒模板在滑至标高13.6m处进行改装,内筒滑模平台在滑至标高10.M 处即可拆除,施工减压锥底板。
Raw materials outside wall shuttering should be refit when it sliding up to 13.6M high Inside wall shuttering should be back out when it sliding up to 10M high,then begin construction of decompress cone bottom board.
2)当全部滑完和不需要外吊架时,即可拆除全部滑模结构。拆除的顺序是:外吊架→外模→外平台→内平台→内模→围檩桁架→千斤顶→提升架,小件由人工拆卸,先集中在顶部再捆绑好吊至地面运走,大件必用吊车配合拆卸,必须先将吊勾挂好才能拆卸以保证安全。
When slip forming work are complete and there is no need lifting frame, it will remove all the slip forming structures. The procedure is: outside scaffold-outside shuttering-outside flat form-inner flat form-inner shuttering-purlin-jack-hoist frame, small items remove by hand, loading to ground then move to store; big items remove by crane, it should hung crane hook as well to ensure safety. 五、滑模模板Shuttering
本工程采用柔性大模板体系的滑升模板,刚度大,板面平整,提升架可在任意位置直接同模板连结,面板采用定型钢模板,再配以调节模板和异形模板。
This project adopted flexible large sliding-up shuttering, stiffness, flat surface. Hoist frame can be connected with shuttering direct at any position. 六、垂直运输 Vertical Transportation
根据计算,本工程筒壁砼:生料库外筒51m3/m,内筒约为50m3/m,因此,现场配
置砼垂直运输设备:1台塔吊和2台混凝土输送泵车。
Based on calculation, this project silo wall concrete: raw materials silo outside 51m3/m, silo inside 50m3/m. site arranged vertical lifting equipment: one tower crane and two concrete conveying trucks.
必要时砼加缓凝剂,控制凝结时间在7~8小时,配合滑模速度,与砼的运输过程和可泵性相适应综合考虑。
I f necessary, it add retarder to control concreting time in 7-8 hours. 七、应急措施及注意事项 Emergency Method and Noticed Proceeding (一) 应急措施 Emergency Method 1、供电:现场备用一台发电机;
Supply Power: One generator stand by on site;
2、混凝土输送:在滑模前,保证现场有一台拖式泵;并制作好两个料斗,在出现意外情况时,用塔吊吊装混凝土;
Concrete Conveying: before slip forming work, ensure one pump, two feed hopper on site. In addition, tower crane for emergency use.
3、安全应急:救护车停靠在现场,在有人中暑时,能随时治疗;
Safety Emergency Method: an ambulance muse parked on site. It will treat patient in time if anyone get heat stroke.
4、下雨:备用充足的塑料布,在下大雨时,对滑模混凝土进行覆盖;
Rain: Prepare enough plastic covering cloth to cover concrete if there is a raining. 5、停滑:当塔吊出现意外情况或其他特殊情况时,不能继续滑升时需考虑停滑。在停滑时,每隔0.5-1.0小时提升1-2个行程,至模板与砼不再粘接(大约4小时),第二天再提升一个行程。
Stop slip forming: when tower crane get accident or special condition, it should be consider stop slip forming. During the stop period, in every interval 0.5-1.0 hour to sliding up 1-2 courses until shuttering do not sticky ( around 4 hours), then sliding up one course on next day.
(二) 施工注意事项Construction attention items
1、库壁滑升是技术性,专业性很强工作,需要周密的安排和强有力的协调。在指挥管理上各工序要有专人负责,明确责任,专人专管,不搞兼职;在分级负责制上,
平台上指挥和平台下指挥对总指挥负责;伙食生活医务等事项由后勤负责人对平台下指挥负责;
Silo wall sliding up is very strict in technology and specialty, and therefore, it must be carefully arranged and effectively coordinated. All the items shall be managed specially by different person with clearly defined responsibility; everybody must work full-time without part-time job. According to the management system, the persons who in charged above and below the platforms are under the leadership of the chief management. The persons who in charged material supply, tests, concrete grading and dosing, concrete mixing, concrete horizontal transport, rebar classification and lifting, accommodation and medicine are under leadership of the one who is responsible for the items below the platform.
2、砼垂直运输、钢筋绑扎、砼浇捣、平台调平、支承杆接长、高度控制、出模砼表面处理、预埋件安放等工作要有业人负责并对平台上指挥负责;工序划分要定人、定岗、定机、定位,明确工作范围,以确保施工顺利进行,保证质量。
The persons who in charged concrete vertical transport, rebar binding, concrete grouting and vibrating, platform leveling correction, prolonging of the supports, height control, surface treatment of the concrete after taking away the formworks, installation of embedded parts of each section are under the leadership of the person who is responsible for the items above the platform.
3、滑模系统折除应在砼浇筑完毕2天后进行,折除以先装后折为原则,折除人员必须服从指挥,带好安全带,按顺序折除,并充分利用塔吊。
The slip form system shall be dismantled 2 days after the concrete grouting has been completed. The working principle is “dismantlement after assemble”, the operators must comply with all the instructions, well fasten the safety belt, dismantlement must be done in right sequence, and take use of tower crane.
八、安全技术措施 Safety Regulation on Site
1、滑模施工主要为高空作业,危险性较大,参加滑模的各位员工必须加强学习,提高
自己的安全意识和安全观念,保证本次滑模施工安全顺利地完成。
Slip form mainly works high above the ground, and very dangerous. Therefore, the staff works for this job must enhance their knowledge and improve their safety consciousness and conception to accomplish the job successfully.
2、进入现场应自觉遵守各种安全规范、规程,严禁酒后、穿拖鞋、硬底鞋等进入现场施工作业;严禁在现场打闹、嬉戏等。
When enter into the jobsite, please comply with all of the safety specifications and regulations. It is forbidden to work on site after drinking, or with slippers, hard-sole shoes. It is not permitted to fight and play on site.
3、经医生检查不宜进入高空作业的人员,严禁上平台进行高空作业;高空施工人员严禁向下扔任何物体,如有物品调运,则必须从井架或塔吊运下。吊运物品时,不准站在平台栏杆以外操作,必要时需将安全带系牢后方可进行操作。
After checked by doctor, the person who is not suitable to work above the ground is forbidden to go with the platform. The staff that works above the ground is forbidden to throw anything to the ground, if it is necessary to transfer something, it must be transferred through head frame or tower crane. When transfer something, the operator must be within the platform handrails and well fasten the safety belt.
4、滑升操作平台组装时必须保证有足够的刚度和稳固性,平台操作人员需随时检查平台的稳固性,发现问题以便及时修整。平台上所有施工人员必须紧密配合,相互照应,所有物件必须平均堆放和不宜过多堆放,以免造成滑升平台失稳;在平台上推料车,搬运物品,倾倒砼等要小心谨慎,宜轻不宜重。
When assemble elevation platform must ensure that it has enough stiffness and
soundness. Flat form operator should check it’s soundness at any time in order to make maintenance in time. Peoples who are working on flat form should cooperate and help each other. All the items should be stock at different place do not keep it at one place to causing flat form over balance. All the people who are working on flat form should be careful of pushing handcart, moving items and pouring concrete and so on.
5、保证和完善各项安全宣传措施,醒目位置设立安全生产宣传牌、标志牌等,滑模高空施工作业时设置施工安全区,安全区用白线明确标明,闲杂人员不得入内。施工现场周边设临时围墙,夜间设灯光照明。
Actions must be taken to ensure and improve safety works, safety production plate and nameplate must be erected in the striking places. During slip form construction above the ground, safety area must be marked definitely by white lines to prevent the entering of the persons not belongs to the working group. The jobsite must be temporarily fenced and installed with electrical lighting for nighttime.
6、加强机械电器设备接地、接零,建筑机械(塔机、井架等)的避雷装置和其他安全限位的管理和整改,实行一机一闸。
Strengthen the connection of earthing of mechanical and electrical equipments and the lightning device and safety limit devices of construction machines (tower crane, head frame etc.).
7、机操人员(包括砼振捣工),特殊工种必须经过培训,持上岗证上班,非操作人员不准动用机电设备。
The machine operators (including vibrating personnel), and special workers shall attend relative trainings, and works with certificates. Non-operator could not touch the mechanical and electrical equipments
8、加强夜间施工照明管理。严禁乱拉接电线,遵守现场用电制度对于电线均应用木杆架设严禁随地拖拉或用钢管搭设,严禁挂在井架或钢管架上。
Strengthen the lighting of works during night. It is forbidden to connect the wires randomly. Comply with the power regulations, the telegraph pole shall be wooden, it could not be dragged everywhere and hung on the head frame or contact with steel pipes.
9、为防止高空坠落,施工过程中“四口”及“五临边”必须设置防护措施。滑模平台、高架平台、挂脚手、上人斜道均设安全网水平、垂直封闭
In order to prevent somebody fall down from high altitude, the four openings and the places nearby shall be equipped with protection advices. The slip form platform, head frame platform and scaffold, chute access shall be vertically and horizontally complete-closed with safety net.
10、各分项施工工序均要制定安全技术措施。项目一般的安全施工措施由项目副经理审查批准,由现场施工员交底后执行。对于重要临时设施、重要施工工序、特殊作业、季节性施工、等项目的安全施工措施须经技术、安全部门审查批准,现场施工员交底后方可执行。
Each constructing procedure should set up safety regulation. Vice site manager inspect and approve safety regulation. Site administrators implement safety regulation. Important temporary construction, important construction procedure, special construction, season construction, project safety regulation should get approve from project and safety department then deliver it to site administrator for implementation.
11、严格贯彻执行防火工作责任制,平台上应根据实际情况配置一定数量的灭火器。 Strictly carry out the fireproofing system, fire extinguisher must be available on the
platform.
12、现场施工必须随时服从项目部统一安排部署,必须严格执行项目部制定的各项安全规章制度。
Site construction must follow Sinoma SCC Project management arrangement and implement all of safety regulation strictly.
相关推荐: