光伏电站项目施工作业指导书
光伏电站项目
编制:审核:批准:日期:施工作业指导书
光伏电站项目施工作业指导书
目 录
一、基本规定.................................................................................................................................................................11.1开工前应具备下列条件:.................................................................................................................................1二、土建工程.................................................................................................................................................................22.1一般规定.............................................................................................................................................................22.2土方工程.............................................................................................................................................................32.3支架基础.............................................................................................................................................................32.4场地及地下设施.................................................................................................................................................62.5建(构)筑物.....................................................................................................................................................7三、安装工程.................................................................................................................................................................83.1一般规定.............................................................................................................................................................83.2支架安装.............................................................................................................................................................93.3光伏组件安装...................................................................................................................................................103.4汇流箱安装.......................................................................................................................................................133.5逆变器安装.......................................................................................................................................................203.6电气二次系统...................................................................................................................................................213.7其它电气设备安装...........................................................................................................................................213.8防雷与接地.......................................................................................................................................................213.9架空线路及电缆...............................................................................................................................................22四、设备和系统调试...................................................................................................................................................234.1一般规定...........................................................................................................................................................234.2光伏组件串测试...............................................................................................................................................234.3逆变器调试.......................................................................................................................................................244.4二次系统调试...................................................................................................................................................264.5其它电气设备调试...........................................................................................................................................28五、消防工程...............................................................................................................................................................295.1一般规定...........................................................................................................................................................295.2火灾自动报警系统...........................................................................................................................................305.3灭火系统...........................................................................................................................................................31六、环保与水土保持...................................................................................................................................................336.1施工环境保护...................................................................................................................................................336.2施工水土保持...................................................................................................................................................34七、安全和职业健康...................................................................................................................................................357.1一般规定...........................................................................................................................................................357.2现场安全文明施工总体规划...........................................................................................................................357.3现场安全施工管理...........................................................................................................................................367.4职业健康管理...................................................................................................................................................367.5应急处理...........................................................................................................................................................37附录A 中间交接签证书.............................................................................................................................................38附录B 光伏组件现场测试表.....................................................................................................................................39附录C 汇流箱回路测试记录表.................................................................................................................................40附录D 并网逆变器现场检查测试表.........................................................................................................................41
光伏电站项目施工作业指导书
一、基本规定
1.1开工前应具备下列条件:
1、在工程开始施工之前,建设单位应取得相关的施工许可文件。2、施工现场应具备水通、电通、路通、电信通及场地平整的条件。 3、施工单位的资质、特殊作业人员资格、施工机械、施工材料、计量器具等应报监理单位或建设单位审查完毕。
4、开工所必需的施工图应通过会审;设计交底应完成;施工组织设计及重大施工方案应已审批;项目划分及质量评定标准应确定。
5、施工单位根据施工总平面布置图要求布置施工临建设施应完毕。6、工程定位测量基准应确立
1.2设备和材料的规格应符合设计要求,不得在工程中使用不合格的设备材料。
1.3进场设备和材料的合格证、说明书、测试记录、附件、备件等均应齐全。 1.4设备和器材的运输、保管,应符合本制度要求;当产品有特殊要求时,应满足产品要求的专门规定。1.5隐蔽工程应符合下列要求:
1、隐蔽工程隐蔽前,施工单位应根据工程质量评定验收标准进行自检,自检合格后向监理方提出验收申请。
2、应经监理工程师验收合格后方可进行隐蔽,隐蔽工程验收签证单应按照现行行业标准《电力建设施工质量验收及评定规程》DL/T5210相关要求的格式进行填写。
1.6施工过程记录及相关试验记录应齐全。
1.7当工程具备验收条件时,应及时申请验收并提交相关验收资料。未经验收或验收不合格的工程不得交付使用或进行后续工程施工。1.8施工现场应设置“五牌一图”,现场围栏应满足相关要求。
0
光伏电站项目施工作业指导书
二、土建工程
2.1一般规定
2.1.1土建工程的施工应按照现行国家标准《建筑工程施工质量验收统一标准》GB 50300的相关规定执行。
2.1.2基坑工程应满足《建筑地基基础施工质量验收规范》GB 50202、《建筑基坑支护规程》JGJ120、《建筑桩基技术规范》JGJ94的要求。
2.1.3测量放线工作应按照现行国家标准《工程测量规范》GB 50026的相关规定执行。
2.1.4土建工程中使用的原材料进厂时,应进行下列检测:
1、原材料进场时应对品种、规格、外观和尺寸进行验收,材料包装应完好,应有产品合格证书、中文说明书及相关性能的检测报告。
2、钢筋进场时,应按现行国家标准《钢筋混凝土用钢》GB 1499等的规定抽取试件作力学性能检验。
3、水泥进场时应对其品种、级别、包装或散装仓号、出厂日期等进行检查,并应对其强度、安定性及其他必要的性能指标进行复验,其质量应符合现行国家标准《通用硅酸盐水泥》GB 175等的规定。
2.1.5当国家规定或合同约定应对材料进行见证检测时或对材料的质量发生争议时,应进行见证检测。
2.1.6原材料进场后应分类进行保管,对钢筋、水泥等材料应存放在能避雨、雪的干燥场所,并应做好各项防护措施。
2.1.7模板及其支架应根据工程结构形式、荷载大小、地基土类别、施工设备和材料供应等条件进行设计、制作。模板及其支架应具有足够的承载能力、刚度和稳定性,能可靠地承受浇筑混凝土的重量、侧压力以及施工荷载。
2.1.8混凝土应严格按照试验室配合比进行拌制,混凝土强度检验应符合《混凝土强度检验评定标准》GB 50107相关规定;混凝土结构工程的施工应符合现行国家标准《混凝土结构工程施工质量验收规范》GB 50204的相关规定。
2.1.9如混凝土中掺用外加剂,相关质量及应用技术应符合现行国家标准《混凝土外加剂》GB 8076、《混凝土外加剂应用技术规范》GB 50119等规定。
1
光伏电站项目施工作业指导书
2.1.10混凝土的冬期施工应符合现行行业标准《建筑工程冬期施工规程》JGJ/T 104的相关规定。
2.1.11混凝土养护应按施工技术方案及时采取有效措施,并应符合下列规定: 1、应在浇筑完毕后的12h以内对混凝土加以覆盖并保湿养护;浇水次数应能保持混凝土处于湿润状态;混凝土养护用水应与拌制用水相同。
2、混凝土浇水养护的时间:对采用硅酸盐水泥、普通硅酸盐水泥或矿渣硅酸盐水泥拌制的混凝土,不得少于7d;对掺用缓凝型外加剂或有抗渗要求的混凝土,不得少于14d。
3、采用塑料薄膜覆盖养护的混凝土,其全部表面应覆盖严密,并应保持塑料布内有凝结水。
2.1.12现浇混凝土基础浇筑结束后,如需进行沉降观测,应及时设立沉降观测标志,做好沉降观测记录。
2.1.13隐蔽工程可包括:混凝土浇筑前的钢筋检查、混凝土基础基槽回填前的质量检查等。隐蔽工程的验收应符合本制度第1.5条的要求。2.2土方工程
2.2.1光伏电站宜随地势而建。当根据图纸设计要求需要进行土方平整时,应按照先进行土方平衡与调配工作,然后再进行测量放线与土方开挖等工作的顺序进行。
2.2.2开挖场地内存在原有的沟道、管线等地下设施时,土方开挖之前应对原有的地下设施做好标记或相应的保护措施。
2.2.3工程施工之前应根据施工设计等资料,建立全场高程控制网及平面控制网。高程控制点与平面控制点应采取必要保护措施,并应定期进行复测。
2.2.4土方开挖宜按照阵列方向通长开挖。在保证基坑安全的前提下,需要回填的土方宜就近堆放,多余的土方应运至弃土场地堆放。
2.2.5土方回填之前应检查回填土的含水量,并分层夯实。对有回填密实度要求的,应试验检测合格。2.3支架基础
2.3.1现浇混凝土支架基础的施工应符合下列规定:
1、在混凝土浇筑前应先进行基槽验收,轴线、基坑尺寸、基底标高应符合
2