武 汉 大 学
土木工程专业专升本(函授)毕业设计任务书
设计题目:房屋建筑工程施工组织设计 专 业: 土木工程 学 号: 姓 名: 指导老师:
武汉大学土木建筑工程学院
20011年3月
1
摘 要
本设计内容为广州某校6号教学楼施工组织设计,核心内容体现于对施工技术的安排。该设计依据现有的施工技术水平和装备、现行施工规范和验收标准以及现场的调查资料等进行编制,具有可操作性,能够切实指导施工生产。
本施工组织设计作为主导施工的依据,编制时对工程量进行了全面计算,围绕“一图三表”及其确定过程,对工程质量、劳动力组织、施工进度计划控制、机械设备及周转材料配备、主要分部分项工程施工方法、安全保证措施、文明施工、降低成本措施等诸多因素尽可能充分考虑,突出科学性及可行性。
本设计为钢筋混凝土框架结构,采用现场浇筑施工。本施工组织设计编制采用较为先进的表格化方法。
设计过程中充分考虑了广州地区的环境因素对工程的影响,并做出了具体的应对措施。广州是亚热带季风性气候,三月到五月份为雨季,进入六、七、八、九月,时有大雨、台风。因此在基坑支护阶段和防止外墙渗漏等进行了特殊安排。对于高温施工时的注意事项也进行了充分的考虑。同时,根据与业主的协商,将本工程的施工时间安排在9月——6月之间,尽可能地降低地区性环境因素对工程的影响。
关键词 建筑
施工组织设计 雨季 高温
II
Abstract
The design content is the construction management plan of the 6th teaching construction in a school of Guangzhou. The core of the content is to arrange construction technology. The design is based on the existing construction technology and equipment, the existing construction norms and acceptance criteria and on-site investigations to establish .It is operational, and it can effectively guide the construction production.
The construction management plan is the basis of the leading construction. We comprehensively calculate the engineering measure when establish . we sufficiently consider the quality of the project, labor organizations the control of construction plans, mechanical equipment and turnover materials, methods of mainly parts of the project construction, safety assurance measures ,civilization construction, measures to reduce the cost and so on around \map three tables\and its determination process, giving prominence to science and feasibility .
The design is the reinforced concrete frame structures, using the construction of casting in site. The construction management plan uses a more advanced form of table method.
We took full account of the effect of environmental factors on the impact of the project in Guangzhou area through the design process, and make a specific measure. Guangzhou is subtropical monsoon climate, and from March to May there will be rainy season. It may suffer them in June, July , August and September. Therefore, special arrangements must be used to the Foundation Pit support stage and prevent the outer wall leakage. We fully considered the noticed issues of construction in the with the owners, the project will be the constructed from September this year to June next year, and we will reduce the effect of local environmental factors on the impact of the project as much as possible.
Keywords :architecture, construction management plan,rainy season,,二~五层层高为4.2m,建筑总高23.1m,室内外高差0.6m。教学实验楼在四大角及正面入口处共设置5部楼梯,在南北角上设置3部电梯。 2、工程结构特点
1
本工程为钢筋砼框架结构,抗震设防烈度为七度,框架抗震等级为二级。建筑物安全等级为二级,建筑结构的安全等级为二级,结构耐久等级为二级。
本工程的主要结构形式见表 1—1。
表 1—1 工程主要结构形式
基础形式 基础持力层 基础 桩承台 柱截面 基础梁截面 形式 主体结构 框架梁 楼板 砼强度等级 结 构 材 料 钢筋 钢材 焊条 砌体 3、安装工程概况
本工程的安装工程有电气照明、电视通讯、自动喷淋报警系统、中央空调系统、给排水系统、供热等。 4、自然条件
工程所在地属亚热带湿润气候区,多年平均降水量947mm。丰水期为6—9月,
2
预制钢筋混凝土方桩基础 至于稍密卵石层上,单板承载力设计值Fk=371KPa 5950mm×4300mm, 9100mm×3850mm, 5950mm × 3850mm, 8050lDI×4900圆圆 350D四x 3500圆 350D四 x 750DIR, 350D四 x 600四 现浇钢筋混凝土框架 12.0m 700x 700mm, 600×600mm, Dl 000m皿 350×950mm、 250×600mln h 350x 750m皿、250X 900mm等 厚l 00mm 梁、培、板:C 30,柱:C40、C 30;构造柱:C 20;垫层:Cl 0 梁、柱、板: I、Ⅱ级钢筋; A 3、 A 3F E43、 E 50系列 烧结空心砖,M5混合砂浆
柱网尺寸 框架柱