SXMB3 项目管理实施规划报审表 ·············································································· 103 SXMB4 施工强制性条文实施计划报审表 ····································································· 108 SXMB5 管理制度报审表 ·························································································· 112 SXMB6 施工进度计划报审表 ···················································································· 113 SXMB7 施工进度调整计划报审表 ·············································································· 114 SXMB8 变更工期报审表 ·························································································· 115 SXMB9 停电申请联系单 ·························································································· 116 SXMB10 工程施工需主网配合停电计划表 ···································································· 117 SXMB11 施工日志 ·································································································· 118 SXMB12 施工周报 ·································································································· 119 SXMB13 施工月报 ·································································································· 120 SXMB14 工程项目交底纲要 ······················································································ 122 SXMB15 甲供设备材料需求计划报审表 ······································································· 123 SXMB16 乙供材料需求计划 ······················································································ 124 SXMB17 工程开工报审表 ························································································· 125 SXMB18 单位(分部)工程开工报审表 ······································································· 126 SXMB19 工程复工申请表 ························································································· 127 SXMB20 工作联系单 ······························································································· 128 SXMB21 会议记录(附件:签到表) ·········································································· 128
SXMB22 文件收发记录表 ·························································································· 129 SXMB23 通用报审表 ······························································································· 130 SXMB24 会议记录问题执行反馈表 ············································································· 131 SXMB25 监理工程师通知回复单 ················································································ 131 SXMB26 工程总结 ·································································································· 132 SXMB27 施工单位启委会汇报表 ················································································ 133 SXMB1施工项目部成立发文
关于成立工程施工项目部的通知
各有关单位、部门:
为确保工程的顺利完成,根据《国家电网公司施工项目部标准化工作手册(330kV及以上变电工程分册)》有关规定,成立工程施工项目部,履行项目管理职责。其人员组成如下:
项目经理:
项目副经理: 项目总工: 项目安全员: 项目质检员: 项目技术员: 项目造价员: 项目部资料信息员: 材料员: 综合管理员: 线路施工协调员:
特此通知
施工单位(章):
年月日
注 本项目部不设置的岗位可不填写。
SXMB2施工项目部管理人员资格报审表
施工项目部管理人员资格报审表
工程名称:编号:
99 / 32
致监理项目部: 现报上本项目部主要施工管理人员及其XX件,请查验。工程进行中如有调整,将重新统计并上报。 XX 附件:相关XX件 施工项目部(章): 项目经理: 日 期: 监理项目部审查意见: 监理项目部(章): 总监理工程师: 日 期: 注本表一式份,由施工项目部填报,业主项目部、监理项目部各一份,施工项目部存份。
岗位 证件名称 证件编号 发证单位 有效期
填写、使用说明
(1)主要施工管理人员包括:项目经理、总工、施工员(仅土建工程需要)专职质检员、专职安全员等。
(2)按有关规定,项目经理、项目总工、专职质检员、专职安全员必须经过相关培训,持证上岗。 (3)施工项目部应对其报审的复印件进行确认,并注明原件存放处。 (4)监理项目部审查要点:
1)主要施工管理人员是否与投标文件一致。 2)人员数量是否满足工程施工管理需要。 3)更换项目经理是否经建设管理单位书面同意。 4)应持证上岗的人员所持证件是否有效。 SXMB3项目管理实施规划报审表
项目管理实施规划报审表
工程名称:编号: