一、工程概况 ································································································································ 2 二、编制依据 ································································································································ 2 三、主要分项工程施工方法 ······························································································· 3 3.1施工测量 ··················································································································· 3 3.2钢筋工程 ··················································································································· 3 3.3模板工程 ··················································································································· 5 3.4螺栓埋件安装 ········································································································· 6 3.5混凝土工程 ·············································································································· 6 四、大体积砼施工技术措施 ······························································································· 8 4.1砼热工计算 ·············································································································· 8 4.2内外温差控制措………………………………………………….10 五、施工机具和人员部署 ·································································································· 11 六、质量保证措施 ··················································································································· 12 七、危险原点的确认与措施…………………………………………13
第1页 共37页
施工方案
一、工程概况
本方案为金华钢厂有限公司---热风炉基础工程的施工方案。工程地点山东东阿金华钢厂有限公司厂内。热风炉基础为全现浇耐热钢筋混凝土结构。由1#、2#、3#热风炉基础和CT-1、CT-2、CT-3、CT-4、CT-5、J-7组成。其中1#、2#、3#热风炉基础为大体积耐热砼,地基处理采用混凝土灌注桩,垫层砼浇筑前,截桩至设计标高,垫层混凝土强度等级为C10,基础为C30耐热
0
混凝土,耐热温度为400C。CT-1、CT-2、CT-3、CT-4、 CT-5、J-7。平面图见附图;
该工程的地质资料由山东泰山地质勘察公司提供。热风炉基础抗震等级为二级,设防烈度为七度。±0.000相当于绝对标高99.65米
二、编制依据
2.1根据S1515G9.1施工图 2.2主要规范规程 序 号 1 2 3 4 5 6 7 8 规范、规程名称 《混凝土结构工程施工质量验收规范》 《工程测量规范》 《建筑地基基础工程施工质量验收规范》 《钢筋焊接及验收规程》 《钢筋机械连接通用技术规程》 《混凝土泵送施工技术规程》 《混凝土外加剂应用技术规范》 《施工现场临时用电安全技术规范》 规范、规程编号 GB50204-2002 GB50026-2007 GB50202-2002 JGJ18-2003 JGJ107-2003 JGJ/T10-95 GB50119-2003 JGJ46-2005 第2页 共37页
2.2有关标准、图籍 序 号 1 2 3 4 规范、规程名称 《建筑工程施工质量验收统一标准》 《混凝土质量控制标准》 《混凝土工程强度检验评定标准》 《平面整体表示方法制图规则和构造详图》 规范、规程编号 GB50300-2001 GB50164-92 GBJ107-87 03G101 2.3有关法规 1 2 3 4 行业 国家 中华人民共和国建筑法 中华人民共和国劳动法 建设工程质量管理条例 建设工程施工现场管理规定 建设部令1991年第15号 2.46相关书籍、资料 1 2 3 建筑施工计算手册(第二版) 建筑施工手册 (第四版) 现行冶金工程施工标准汇编 中国建筑工业出版社 中国建筑工业出版社 冶金工业出版社
三、主要分项工程施工方法 3.1施工测量
根据该工程的精度要求,我项目部为该工程配备了南方全站仪、电子经纬仪TDJ2E两台、水准仪DZS3-1两台、50m钢卷尺两把,且已由质量检测站进行检定,符合工程测量(GB50026-93)规范要求。
3.1.1施工测量控制网及高程控制
根据热风炉基础桩平面布置图和高炉基础中心线,热风炉基础的轴线,并利建设单位提供的3个控制点 及热风炉坐标对热风炉基础轴线进行定位和复核。 3.1钢筋工程
根据图纸设计,该工程选用的钢筋分别为一级钢HPB235规
第3页 共37页
格为?8、10,二级钢HRB335规格为Φ12、16、20、25。 3.2.1钢筋原材料进场
1)钢筋进场时,必须随带合格证原件,并应对其外观进行检查,表观应平直、无损伤、表面不得有裂纹、油污、颗粒状或片状老锈,经检查合格后,方可进场;
2)钢筋进场后,应分类堆放,放置在指定位置,以防锈蚀,且钢筋应分别挂牌标识,注明产地、级别、直径、炉批号、检验状态;
3)钢筋进场后,每批钢筋必须按有关规范要求抽样复检,复检合格后,方可投入使用。 3.2.2钢筋制作加工
1)Ⅰ级钢筋采用切断机切断,人工成型,Ⅱ级钢筋采用切断机切断,成型机成型;
2)盘园钢筋采用钢筋调直机进行拉伸调直,其拉伸率≤3%; 3)钢筋制作时,HPB235级钢筋应作180度弯钩,其弯弧内直径不应小于钢筋直径的2.5倍,弯钩弯钩平直部分长度不应小于钢筋直径的3倍;
4)箍筋弯钩平直部分的长度≥10d,弯折角度应为135度。 3.2.3钢筋连接和安装
该工程的钢筋连接采用电渣压力焊和搭接两种连接方式。钢筋锚固长度la:HPB235为24d,HRB335为30d。钢筋搭接长度ll:基础顶层钢筋为1.4la,接头百分率≤50%。钢筋搭接同一区段的长度为1.3ll。机械连接同一区段的长度35d,接头率≤50%。
1)本工程钢筋连接Φ25(含Φ25)以上采用闪光对焊连接,由于长度较大不利于施工,所以在长度范围内可以设一个搭结头。
3.2.4钢筋绑扎安装
1)钢筋采用人工绑扎,用22#铁线将钢筋绑扎牢固。基础底板必须满绑,绑丝长度不小于380mm;
2)双向受力板主筋每个交点必须绑扎牢固,并且相互扣成八字形;
3)为保证热风炉基础底板顶部钢筋位置的准确,保证钢筋有效截面,需用DN48钢管设置马凳 (详见附图),杯口模板采用复合多层板进行组拼。
第4页 共37页